OngoingActive

Saubhagyam

Lucknow, Uttar Pradesh
15-09-2010Launch Date
OngoingType
UPRERAPRJ3783RERA ID
10-07-2020Completion Date

Basic Details

Project TypeOngoing
Project CategoryResidential
Total area in round figure (Sq.mt.)33637
Project NameSaubhagyam
Registration Fee (in Rs.)173500
AddressNot specified
Village/Locality/Sector etc.Not specified
StateUttar Pradesh
Project Duration (In month)118
DistrictLucknow
Original Start Date15-09-2010
TehsilLucknow
Proposed Start Date15-09-2010
Sanctioning Competent AuthorityU.P. Awas Evam Vikas Parishad
Project Cost (in Lacs)20532
Proposed Completion Date10-07-2020

Location

Latitude

26.768403955721705

Longitude

80.96034812071933

Bank Details

Account no.6193002900000013
Name Of Account HolderOMNI FARMS PVT LTD
Bank NamePunjab National Bank
Branch AddressVibhuti Khand, Gomti Nagar,Lucknow-226010
Branch NameVibhuti Khand Branch
IFSC CodePUNB0619300

Development Works

Demarcation of Plots

DEMARCATED AT LOCATION

Boundary Wall

CONSTRUCTED

Road Work

24/18 MT. APPROACH ROADS AVAILABLE. 6M. INTERNAL ROAD CONSTRUCTED AS PER APPROVED LAYOUT.

Footpaths

1.2 - 1.5M. WIDE PAVING ALONG INTERNAL ROAD.

Water Supply Including Drinking Water Facilities

UNDERGROUND WATER THROUGH TERRACE TANKS/ U.G. TANK.

Sewer System

MAIN SEWER AVAILABLE CONNECTED TO TOWNSHIP (VRINDAVAN YOJANA- HOUSING BOARD) SEWER

Drain

K.C./ U-DRAINS PROPOSED CONNECTED TO TOWNSHIP (VRINDAVAN YOJANA- HOUSING BOARD) DRAINAGE

Parks

GREEN AREAS AS PER APPROVED LAYOUT

Tree Planting

SHRUBS, GRASS & TREES UPTO 6M. HIGH

Design For Electric Supply Including Street Lighting

SUPPLY FROM NEAR BY SUB-STATION AVAILABLE. EFFICIENT STREET LIGHTING

Community Buildings

CLUB CONSTRUCTED WITH SWIMMING POOL

Treatment and Disposal System of Sewage and Sullage water

TOWNSHIP (VRINDAVAN YOJANA- HOUSING BOARD) S.T.P. AVAILABLE

Solid Waste Management And Disposal System

NAGAR NIGAM, LUCKNOW

Water Conservation System

RAIN WATER HARVESTING PROVISIONS AT SITE.

Energy Management System Including Use of Renewable Energy

20% OF STREET LIGHT TO HAVE SOLAR ENERGY BACK-UP

Fire Protection And Fire Safety System

WORK DONE AS PER FIRE N.O.C. DRAWING

Social Infrastructure And Other Public Amenities Including Public Health Services

NA

Emergency Evacuation Services

FIRE ESCAPE IN EACH BLOCK.

Other Miscellaneous Work

NA

Documents

Sale Deed

No: 6162 | Date: 02-04-2016

Details of Encumbrances

Uploaded: 27-02-2019

Commencement Certificate

Uploaded: 04-07-2018

Other Plan(If Any)

Uploaded: 30-07-2018

Proforma of Application Form

Uploaded: 31-07-2018

Proforma of Allotment Letter

Uploaded: 27-02-2019

Proforma of Conveyance Deed

Uploaded: 04-07-2018

Proforma of Completion Certificate(Occupancy)

Uploaded: 06-07-2018

Waste Disposal Plan

Uploaded: 04-07-2018

Water Supply Plan

Uploaded: 04-07-2018

Electricity Supply Plan

Uploaded: 04-07-2018

Development Work Plan

Uploaded: 04-07-2018

Affidavit

Uploaded: 06-07-2018

CA CERTIFICATE

Uploaded: 10-07-2018

ARCHITECT CERTIFICATE

Uploaded: 10-07-2018

ENGINEERS CERTIFICATE

Uploaded: 10-07-2018

Registry Document In Case of Own Land

Uploaded: 28-07-2017

Authentic copy of Approval of Project

Uploaded: 28-07-2017

Sanctioned Layout Plan (Of Entire Project)

Uploaded: 28-07-2017

Sanctioned Building/ Block Plan (Add Plans for All Buildings or Blocks)

Uploaded: 28-07-2017

Commencement Certificate

Uploaded: 28-07-2017

Floor plans of all types

Uploaded: 28-07-2017

Waste Disposal Plan

Uploaded: 28-07-2017

Water Supply Plan

Uploaded: 28-07-2017

Development Work Plan

Uploaded: 28-07-2017

Electricity Supply Plan

Uploaded: 28-07-2017

Affidavit

Uploaded: 28-07-2017

Permits

Orignal Permit No994
Orignal Permit Date18-04-2016
Valid Upto12-07-2016
Revalidated Permit No-
Revalidated Permit Date-
Revalidated Permit Valid Upto-
Permit Extendable Upto11-07-2019
End Date10-07-2020
Uploaded Approve LayoutOpen
Uploaded Sanctioned LetterOpen
Uploaded Approved MapOpen
Uploaded Floor Plan Of All TypesOpen
Uploaded Project SpecificationsOpen
Uploaded Sajra DetailNot Specified

Project Team

Contractor Name (if any)Prabha Enterprises
Contractor Address182-C, Udyan 1, Bangla Bazaar, Lucknow
Architect NameESpaces
Architect Address108, FF, Corporate Chamber- I, Vibhuti Khand, Lucknow
Architect Licence NumberCA/89/12382
Structural Engineer NameSpace Combine
Structural Engineer AddressAI/112, Safdarjung Enclave, New Delhi
Mobile number(Project Co-ordinator)9670222298

Land Details

AFS

Showing 8 blocks with 348 units

Property Summary

Total Area

55598.37

598455.29 ft²

Total Units

687

7 different types

Blocks & Floors

8

15 floors across all blocks

Parking

0

0 garages, 0 open

Average unit size:80.93
Balconies:714
Parking ratio:0.00 per unit

Block SAUBHAGYAM-TI

29 units

Block SAUBHAGYAM-T2

43 units

Block SAUBHAGYAM-T6

35 units

Block SAUBHAGYAM-T7

38 units

Block SAUBHAGYAM-T9

40 units

Block SAUBHAGYAM-T10

85 units

Block SAUBHAGYAM-T11

71 units

Block SAUBHAGYAM ARCADE

7 units

Khasra Details

Total Area

44609.67

480174.03 ft²

1 plot
Plot
TypePlot
Khasra/Plot No9D/GH-1
Area(In Sq. Mt.)44609.67

Account Closure Details

Processing Time

750 days

From application to approval

Application Submitted

19-01-2022

Application Approved

08-02-2024

Other Details

Contractor Name (if any)Prabha Enterprises
Contractor Address182-C, Udyan 1, Bangla Bazaar, Lucknow
Architect NameESpaces
Architect Address108, FF, Corporate Chamber- I, Vibhuti Khand, Lucknow
Architect Licence NumberCA/89/12382
Structural Engineer NameSpace Combine
Structural Engineer AddressAI/112, Safdarjung Enclave, New Delhi
Mobile number(Project Co-ordinator)9670222298