25.455530
78.621052
Under process. 8 plot demarcation completed as on date
60 percent already completed with 7ft height including main gate.
25 percent Road construction in progress for whole site.
Not commenced.
Not commenced.
Not commenced.
Not commenced.
40 percent park completed and 60 percent boundary work of park done
40 percent complete
not yet started
Not commenced.
Not commenced.
Not commenced.
Not commenced.
Not commenced.
none since villa system
none
not applicable since villa only
Work in progress for sample villas. Commercial Property is not for sale and for own use so not included in Plan details uploaded.
No: Owner-Developer agreement with city college | Date: 10-09-2019
No: Explanations about the project | Date: 23-10-2020
Total Area
26360.00 m²
283736.40 ft²