26.52728
80.24335
To be marked properly with Brick edges and marked with a stone plaque, part front plot boundary wall is to built.
Only one side boundary wall is there. it will be done in precast.
Soil is compressed. 2 broken stone layers then a PCC layer and finishing with the metal/ bitumin mix layer is to come.
With soil dressing and top finished with soft tiles.
Lines to be laid as per the submitted plan and finally connected to a overhead tank.
Lines to be laid as per the submitted plan and finally connecting it to STP.
Small drains and big nallah are to be built and part of it to be connected to Rain Water Harvesting pits as mentioned in the plans.
Parks with grass, plants and garden gyms. Sizes as per specified in the plan.
To be done along the road as well as in the parks.
As per specified in the Electrical plan. The street light to be fixed complimenting the landscaping futures.
N.A.
S.T.P.
Provisions are being made for it to be carried out of the site through a competent agency.
Rain Water Harvesting system. water recharge pits as well as a system to reuse the waste water in the landscape is being developed.
A suggestion plan is being created for the household to promote the use of solar units as backups.
Hydrants to be put along the water supply lines.
Not available in this phase
Wide roads and ample open areas.
N.A.
Showing 1 blocks with 4 units
Total Area
0.00 m²
0.00 ft²
Total Units
0
1 different types
Blocks & Floors
1
1 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
59754.00 m²
643186.08 ft²