26.70908
83.41076
Blocks have been demarcated at site and work is in progress
boundary wall has been constructed at site
Bituminous roads has been proposed. Trunk roads construction work is in progress. Link roads will be constructed after the construction of blocks
footpaths have been provisioned and shall be constructed after the construction of blocks
Trunk water supply lines for feeding these blocks are being laid.
Trunk lines are being laid at site. sewer lines will be laid at the end of construction of blocks
R.C.C. Trunk drains construction work is going on at site. Once the construction of blocks is over these lines shall be connected to the system
n/a
Plantation shall be taken up after the construction of blocks and development of site
Electrical load as per UPPCL shall be sanctioned, installed, and shall be handed over to UPPCL for maintenance
N/A
Primary treatment at block level through STP, secondary treatment proposed at STP
garbage collection centre proposed at site
N/A
N/A
N/A
N/A
N/A
N/A
Showing 3 blocks with 14 units
Total Area
2617.34 m²
28172.79 ft²
Total Units
44
2 different types
Blocks & Floors
3
4 floors across all blocks
Parking
0
0 garages, 0 open