NewActive

Golden Gateway

Mathura, Uttar Pradesh
25-11-2022Completion
NewType
MathuraDistrict
229 LCost

Basic Details

Project Type:New
Project Category:Commercial
Total area in round figure (Sq.mt.):5914
Project Name:Golden Gateway
Registration Fee (in Rs.):70000
Address:Not specified
Village/Locality/Sector etc.:Not specified
State:Uttar Pradesh
Project Duration (In month):35
District:Mathura
Original Start Date:-
Tehsil:Mathura
Proposed Start Date:02-01-2020
Sanctioning Competent Authority:Mathura-Vrindavan Development Authority
Project Cost (in Lacs):229
Proposed Completion Date:25-11-2022

Location

Latitude

27'34’21.36”N, 77'37’21.37”E

Longitude

27'34’19.65”N, 77'37’19.57”E

Bank Details

Account Details
Name of the Account:GOLDEN GATEWAY
Account Number:920020001268837
Bank Name:AXIS BANK LTD.
Branch Name:FARIDABAD B.K. CHOWK
Branch Address:FARIDABAD BK CH HR, FARIDABAD 121001
Branch State:Uttar Pradesh
Branch District:Mathura
IFSC Code:UTIB0003202
Transaction Account Details
Name of the Account:GOLDEN GATEWAY
Account Number:919020068437315
Bank Name:AXIS BANK LTD.
Branch Name:FARIDABAD B.K. CHOWK
Branch Address:FARIDABAD BK CH FAR HR, FARIDABAD 121001
Branch State:Uttar Pradesh
Branch District:Mathura
IFSC Code:UTIB0003202

Development Works

Demarcation of Plots

Commercial plots of different sizes as approved by the authority and detailed in the annexure are demarcated on ground.

Boundary Wall

No boundary wall is been provided by the developer for the individual plots. The boundary wall will be constructed by the buyers.

Road Work

All sub arteries will have flexible pavements of desired thickness of base and sub base course depending upon the CBR value of the soil underneath.

Footpaths

All roads will have footpaths in the shoulder and these footpaths will be finished with the material which will allow rain water percolation into the soil below.

Water Supply Including Drinking Water Facilities

Potable water will be supplied by developer of the SUNCITY ANANTAM HI-TECH CITY as this development is an integral part of the approved layout of this Hi-Tech Township.

Sewer System

A network of design dia of SWG pipes with chambers and manholes will be laid in front of all plots and the network will be connected to the trunk mains laid by the developer of HI-TECH CITY as this development is an integral part of the approved Hi-Tech Township.

Drain

Dual network, one for roof top rain water connected to the rain water harvesting pits provided at different locations as per the design and the overflow of the rain water harvesting pits will be connected to the external drainage networks which will be provided to carry the road and pot run-offs and finally will be connected to the trunk network of SUNCITY ANANTAM HI-TECH CITY being developed by the hi tech developer as this development is an integral part of this HI-TECH CITY.

Parks

All the parks as proposed in the approved layout will be developed with provision of tot-lot areas, activity areas, lawns, jogging tracks, shrubs and shady trees as per the design.

Tree Planting

Trees of different species will be planted along the roads and the species of trees will be more or less of the similar types which already exist in the surrounding area of this township.

Design For Electric Supply Including Street Lighting

The electrical network design for the township will be as per Indian Electricity Act and Rules, guidelines and regulation of U.P. Electricity Supply code 2005 and regulation of U.P. Electricity Regulatory Commission for electricity distribution networks in townships. The source of supply for township will be from the network to be laid by the SUNCITY ANANTAM HI-TECH CITY developer as per Hi-Tech Policy of Govt. of U.P. The network in our plotted development will be mainly underground, both for HT/LT, the distribution will be on 11/.4 kva. For this, transformers if required will be provided by us. As far as possible LED electrical fixtures will be used on swedged poles along all the roads in our plot. The distance between poles and their heights will be regulated by the uniform desired lux levels without dark spots on the roads. The lux level will be guided by the relevant codes for street lighting.

Community Buildings

As the population of this plotted development is already accounted for in the population of HI-TECH CITY and corresponding to this population all the community sites are provided by the developer as per the approved layout is this HI-TECH CITY.

Treatment and Disposal System of Sewage and Sullage water

As the trunk network and STP for the township is been developed by the developer of the HI-TECH CITY the required capacity of STPs are been provided by him. We are only linking our network to the trunk network laid by the developer.

Solid Waste Management And Disposal System

Door to door collection of solid waste arrangement will be made in this plotted development through the maintenance agency which will be assigned maintenance of this plotted development. Besides this, garbage bins and collection points will be provided in this plotted development. The disposal of the same will be through the local municipality for organising solid waste disposal of this plotted development and for the same the developer of this HI-TECH CITY will enter into an agreement with the local municipality.

Water Conservation System

Rain water harvesting pit with numbers and size based on the design at different locations will be provided in the plotted development and only the overflow of these pits will be drained through the external drainage network into the trunk drains laid by the HI-TECH developer. The re-cycled water from the STPs will be made available by the developer of the HI-TECH CITY of which this plotted development is a part and the same water will be used for irrigation purposes, car washing purposes, etc. to decrease the fresh water requirement of this plotted development.

Energy Management System Including Use of Renewable Energy

LED luminaries will be used in the township and solar energy will be used for illuminating these LED luminaries and lighting in the park.

Fire Protection And Fire Safety System

As this plotted development is an integral part of the HI-TECH CITY being developed by the HI-TECH CITY developer, underground water tanks for the water required for fire fighting have been provided along with the fire hydrants so that in the event of emergency water can be drawn from thee hydrants by the fire department.

Social Infrastructure And Other Public Amenities Including Public Health Services

As this plotted development is an integral part of SUNCITY ANANTAM HI-TECH CITY being developed by the HI-TECH CITY developer, the required number of social infrastructure like school, community centres, health centres, baal kalyan centres, blood bank plots have been provided as per the approved layout of the HI-TECH CITY.

Emergency Evacuation Services

As this is a plotted development with parks and reasonably sized open areas, so evacuation will not be a problem.

Other Miscellaneous Work

The HI-TECH CITY of which this plotted development is a part is being developed with a reasonably sized greens and neighbourhood sports activity centre.

New Documents

Sale Deed

No: 15484 | Date: 24-10-2019

Uploaded Documents

Commencement Certificate

Proforma of Completion Certificate(Occupancy)

Waste Disposal Plan

Water Supply Plan

CA CERTIFICATE

ARCHITECT CERTIFICATE

ENGINEERS CERTIFICATE

ENGINEERS CERTIFICATE

ENGINEERS CERTIFICATE

ENGINEERS CERTIFICATE

ENGINEERS CERTIFICATE

ENGINEERS CERTIFICATE

Details of Encumbrances

Uploaded: 18-11-2019

Commencement Certificate

Uploaded: 13-12-2019

Other Plan(If Any)

Uploaded: 18-11-2019

Proforma of Application Form

Uploaded: 18-11-2019

Proforma of Allotment Letter

Uploaded: 18-11-2019

Proforma of Conveyance Deed

Uploaded: 18-11-2019

Proforma of Completion Certificate(Occupancy)

Uploaded: 13-12-2019

Waste Disposal Plan

Uploaded: 30-11-2019

Water Supply Plan

Uploaded: 30-11-2019

Electricity Supply Plan

Uploaded: 18-11-2019

Development Work Plan

Uploaded: 30-11-2019

Affidavit

Uploaded: 18-11-2019

CA CERTIFICATE

Uploaded: 12-12-2019

ARCHITECT CERTIFICATE

Uploaded: 13-12-2019

ENGINEERS CERTIFICATE

Uploaded: 13-12-2019

Permits

Orignal Permit No10/V/16-17
Orignal Permit Date27-05-2017
Valid Upto26-05-2022
Permit Extendable Upto26-05-2022
End Date26-05-2022

Project Team

Contractor Name (if any)Shailendar Sharma
Contractor AddressShri Krishna Infradesign Pvt. Ltd., Sector-2/92, Near Golchakkar, Rukmani Vihar, Vrindavan Mathura
Architect NameSwapna Dipanker Nath
Architect AddressDesign Collaborative Consulting, 512, Aggarwal Prestige Mall, Road 44, Plot 2, Near M2K, Pitampura, Delhi 110034
Architect Licence NumberCA/2005/36281
Structural Engineer NameShailendar Sharma
Structural Engineer AddressShri Krishna Infradesign Pvt. Ltd., Sector-2/92, Near Golchakkar, Rukmani Vihar, Vrindavan Mathura
Mobile number(Project Co-ordinator)9818473291

Project Land Details

Plot

Showing 1 blocks with 3 units

Property Summary

Total Area

0.00

0.00 ft²

Total Units

0

1 different types

Blocks & Floors

1

1 floors across all blocks

Parking

0

0 garages, 0 open

Average unit size:NaN
Balconies:0
Parking ratio:NaN per unit

Block undefined

3 units

Khasra Details

Total Area

5914.00

63657.70 ft²

1 plot
Khasra
Type:Khasra
Khasra/Plot No:2126
Area(In Sq. Mt.):5914

Other Details

Contractor Name (if any):Shailendar Sharma
Contractor Address:Shri Krishna Infradesign Pvt. Ltd., Sector-2/92, Near Golchakkar, Rukmani Vihar, Vrindavan Mathura
Architect Name:Swapna Dipanker Nath
Architect Address:Design Collaborative Consulting, 512, Aggarwal Prestige Mall, Road 44, Plot 2, Near M2K, Pitampura, Delhi 110034
Architect Licence Number:CA/2005/36281
Structural Engineer Name:Shailendar Sharma
Structural Engineer Address:Shri Krishna Infradesign Pvt. Ltd., Sector-2/92, Near Golchakkar, Rukmani Vihar, Vrindavan Mathura
Mobile number(Project Co-ordinator):9818473291