NewActive

Belvedere Suites (GH-12) Integrated Township

Lucknow, Uttar Pradesh
30-09-2026Completion
NewType
LucknowDistrict
12286 LCost

Basic Details

Project Type:New
Project Category:Residential
Total area in round figure (Sq.mt.):6541
Project Name:Belvedere Suites (GH-12) Integrated Township
Registration Fee (in Rs.):38000
Address:Not specified
Village/Locality/Sector etc.:Not specified
State:Uttar Pradesh
Project Duration (In month):48
District:Lucknow
Original Start Date:-
Tehsil:Lucknow
Proposed Start Date:01-10-2022
Sanctioning Competent Authority:Lucknow Development Authority
Project Cost (in Lacs):12286
Proposed Completion Date:30-09-2026

Location

Latitude

26.826380

Longitude

81.022734

Bank Details

Account no.:50200027303224
Name Of Account Holder:M/S ANS DPL SEP A/C BELVEDERE SUITES GH-12
Bank Name:HDFC Bank
Branch Address:Vibhuti Khand, Gomti Nagar, Lucknow
Branch Name:Vibhuti Khand, Gomti Nagar, Lucknow
IFSC Code:HDFC0004805

Development Works

Demarcation of Plots

As per approved sanction plan.This is single plot traingle shaped , having total 1 no. of entry gate and 1no. of exit gate from the 45 mtr wide front road and 30 mtr internal road. Site is surronded by 45 mtr road and 30 mtr road from North and West respectively and a green plot from East side.

Boundary Wall

1.8 - 2.1m high and 200 mm thick Boundary wall designed . Brick Work of 9inches and rcc work in column and beam may be used as per design. MS Broad entrance and exit gates are developed with boundary.

Road Work

Trimix / asphalt road will be used as per deisgn suggested by the Architect for internal road.

Footpaths

All internal roads will have narrow footpath with matt finish tiles pavers or equivalent finishes as per landscape design.

Water Supply Including Drinking Water Facilities

All apartments shall be provided with domestic water for household activities and STP treated water for flushing. Ground water may also be used and user can have their individual RO system as per their requirement.The STP treated water shall also be supplied for irrigation purposes. For the same water tanks are getting created in underground and on terrace. Separate tanks are provided for fire water.

Sewer System

Centralized Sewerage system shall be Provided. All Sewerage water shall go to the STP for treatement. after treatement ,water shall be recycled and it will use in gardening, flush tanks and vehicle washing, oveflow from the STP shall be connect with the Municiple sewarage system.

Drain

Storm water system shall be Provided. Storm water from Roads and other lanscape area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municiple drain line.

Parks

There is a significant green area beside building including green parks, play areas for childrens and different recretional activities.

Tree Planting

The trees of category ornamental ,shady and native species shall be planted in the entire project as per the species recommende in the landscape in order to maintatin greenary and natural view.

Design For Electric Supply Including Street Lighting

We have designed the system as per local electricity Board and consider centralized Transformer,HT panel,LT Panel,Feeder Pillar and DG back for common service like External lighting with timer control,STP,Pump room etc.

Community Buildings

Fully centralised AC Club House/community center is proposed, swimming pool and some temporary kiosks on the central atrium with sitting area of each building. Club comprises of mini-theatre,spa with steam and sauna ,swimming pools with changing rooms,yoga/medidation room, multipurpose hall ,Gymanasium,squash court,indoor playing areas etc.

Treatment and Disposal System of Sewage and Sullage water

Centralized Sewerage system for entire project and all towers shall be connected to STP . All Sewerage water shall go to the STP for tretement after treatement ,water shall be recycle and it will use in gardening, flush tanks and vehicle washing, oveflow from the STP shall be connect with the Municiple sewarage system.

Solid Waste Management And Disposal System

Project shall have  waste segregation area and OWC for treatment of organic waste.The solid waste shall be encouraged for segregation with in all apartments. the dustbins shall be provided for segregated waste in the common areas. from where the bio waste shall be converted to manure through owc within the campus and other waste shall be handed over to the government vendors for further disposal.

Water Conservation System

A well designed rain water harvesting system shall be provided for the whole building complex to conserve water by ensuring adequate nos. of  recharge pits

Energy Management System Including Use of Renewable Energy

We will use LED lights fitting in external area as well as solar lights. In STP and Pump room all the equipment shall have energy efficient motor. 25 % of Terrace is covered with Solar Voltaic Panels to provide Renewable source of energy for common areas in building complex. Also timer control panels shall be used for efficient energy managemen.

Fire Protection And Fire Safety System

All Fire norms shall be followed as per NBC code and approval of fire department. fire sprinklers,smoke detectors,FHC with pumps are provided as per norms.

Social Infrastructure And Other Public Amenities Including Public Health Services

The Social infrastructure shall be provided with domestic water supply with tanks,STP treted water for flushing with tanks and irrigation ,storm /rain water drainage system,sewer drainage system,waste water drainage system,firefighting system including sprinklers ,FHC detectors ,fire water tank ,authority main power supply ,Dg power backup for essential common supply,lifts.

Emergency Evacuation Services

Fire Staricase is provided in the each building, with fire resistant doors, basements have 1 (one) accesse and exit in case of emergency. Dedicated assembly areas are also defined in the campus.Adequate signage is also provided.

Other Miscellaneous Work

Not applicable

New Documents

Registry Document

No: 4798 | Date: 09-04-2015

Sale Deed

No: 10650 | Date: 13-07-2015

Sale Deed

No: 10036 | Date: 30-06-2015

Registry Document

No: 5396 | Date: 18-04-2015

Extract of Khatauni

No: Khatauni extracts of all Khasra of the project land | Date: -

Extract of Khatauni

No: Land Area Details - Belvedere Suits GH-12 | Date: -

Extract of Khatauni

No: Reply to objection Letter - GH-12 | Date: -

Extract of Khatauni

No: Reply to 2nd query letter_Affidavit attached - Belvedere Suites GH-12 | Date: -

Extract of Khatauni

No: LDA Letter for 28 floor plan sanctioned | Date: -

Extract of Khatauni

No: LDA Letter for clarification of 28 floor plan of the project Belvedere Suites GH-12 | Date: -

Extract of Khatauni

No: Request Letter to The Secretary, RERA for grant of registration no. for GH-12, LDA letter attached | Date: -

Uploaded Documents

Other Plan(If Any)

Proforma of Completion Certificate(Occupancy)

Details of Encumbrances

Uploaded: 22-04-2022

Commencement Certificate

Uploaded: 30-05-2022

Other Plan(If Any)

Uploaded: 07-05-2022

Proforma of Application Form

Uploaded: 22-04-2022

Proforma of Allotment Letter

Uploaded: 22-04-2022

Proforma of Conveyance Deed

Uploaded: 22-04-2022

Waste Disposal Plan

Uploaded: 21-04-2022

Water Supply Plan

Uploaded: 22-04-2022

Electricity Supply Plan

Uploaded: 22-04-2022

Development Work Plan

Uploaded: 21-04-2022

Affidavit

Uploaded: 19-04-2022

CA CERTIFICATE

Uploaded: 22-04-2022

ARCHITECT CERTIFICATE

Uploaded: 19-04-2022

ENGINEERS CERTIFICATE

Uploaded: 19-04-2022

Other

Uploaded: 21-04-2022

Permits

Orignal Permit NoGroup Housing/04646/LDA/BP/21-22/1571/30032022
Orignal Permit Date23-04-2022
Valid Upto22-04-2027
Permit Extendable Upto22-04-2030
End Date30-09-2026

Project Team

Contractor Name (if any)Rajesh Tiwari - Prabha Enterprises
Contractor Address182-C, Eldeco Udyan-1, Lucknow-226002
Architect NameMr. Rudraksha Charan
Architect AddressD-102, Chhatarpur, New Delhi-110074
Architect Licence NumberCA/2011/53000
Structural Engineer NameMr. Sanjeev Jain
Structural Engineer AddressI-1738, Chittaranjan Park, New Delhi-110019
Mobile number(Project Co-ordinator)9891042472

Project Land Details

AFS

Showing 1 blocks with 56 units

Property Summary

Total Area

17386.20

187143.32 ft²

Total Units

90

2 different types

Blocks & Floors

1

29 floors across all blocks

Parking

0

0 garages, 0 open

Average unit size:193.18
Balconies:273
Parking ratio:0.00 per unit

Block Tower A

56 units

Khasra Details

Total Area

6541.00

70406.67 ft²

1 plot
Khasra
Type:Khasra
Khasra/Plot No:91, 93, 321, 327, 322, 323
Area(In Sq. Mt.):6541

Other Details

Contractor Name (if any):Rajesh Tiwari - Prabha Enterprises
Contractor Address:182-C, Eldeco Udyan-1, Lucknow-226002
Architect Name:Mr. Rudraksha Charan
Architect Address:D-102, Chhatarpur, New Delhi-110074
Architect Licence Number:CA/2011/53000
Structural Engineer Name:Mr. Sanjeev Jain
Structural Engineer Address:I-1738, Chittaranjan Park, New Delhi-110019
Mobile number(Project Co-ordinator):9891042472