HUDA CONSTRUCTION WATER NOCDate: 30-10-2018Status: ALREADY BEEN OBTAINED
ELECTRICAL LOAD AVAILABILITYDate: 15-10-2018Status: ALREADY BEEN OBTAINED
AIRPORT HEIGHT CLEARANCE NOCDate: 22-10-2018Status: ALREADY BEEN OBTAINED
LICENSEDate: 25-02-2018Status: ALREADY BEEN OBTAINED
ENVIRONMENTAL CLEARANCEDate: 07-02-2019Status: ALREADY BEEN OBTAINED
FOREST NOCDate: 26-07-2018Status: ALREADY BEEN OBTAINED
TREE CUTTING PERMISSIONDate: 23-10-2018Status: APPLIED FOR BUT YET TO RECEIVE
CONSENT TO ESTABLISHDate: 12-02-2019Status: APPLIED FOR BUT YET TO RECEIVE
CONSENT TO OPERATE NOCDate: NAStatus: YET TO FILE FOR APPROVAL
DEED OF DECLARATIONDate: NAStatus: YET TO FILE FOR APPROVAL
EXECUTION OF SALE DEEDDate: NAStatus: YET TO FILE FOR APPROVAL
MINING PERMISSIONDate: 01-09-2019Status: YET TO FILE FOR APPROVAL
FIRE SCHEME APPROVALDate: 28-02-2019Status: YET TO FILE FOR APPROVAL
SERVICES ESTIMATES AND PLANSDate: 28-02-2019Status: YET TO FILE FOR APPROVAL
OCCUPATION PERMISSION INCLUDING FIRE NOC, HSVP INTERNAL AND EXTERNAL SERVICES NOC, LIFT NOC, CHIEF ELECTRICAL ENGINEER NOC AND ANY OTHER REQUIRED APPROVALDate: NAStatus: YET TO FILE FOR APPROVAL
GMDA/ HUDA/ MCG SERVICES CONNECTION PERMISSIONDate: NAStatus: YET TO FILE FOR APPROVAL
ELECTRICAL LOAD CONNECTION/ ENERGIZATIONDate: NAStatus: YET TO FILE FOR APPROVAL
HSD STORAGE NOCDate: NAStatus: YET TO FILE FOR APPROVAL