Plot boundaries as per given by AVAS Vikas Authority .
Temporary Steel Fencing done for construction work, and Permanent Boundary wall to be provided after construction.
Paved roads will be provided.
Pavers will be provided.
Raw water will be received in under ground tank, then processed in water treatment plant, and treated water stored in tanks.
Underground sewage system. Feeder pipeline of UPVC and final discharge through RCC pipes.
Strom water will go to harvesting recharge pits. Excess water if any, will be discharge to authority drain.
It shall provided as per approved plan.
20 Nos of tree planting will be done as per approved plan.
HT line shall be taken from UPPCL, converted to LT supply With in house transformers and a switching system. Street lights shall be LED based.
Club house with Spa, Gym, and Swimming Pool, will be provided as approved drawing.
Treatment plan not applicable, Sewage will be discharge to authority drain.
Kitchen waste collection will be collected manually. Other waste shall be manually handle for disposal.
Harvesting recharge pits shall be used . Water filtration is to be done as per requirement.
Electricity to be supplied by the UPPCL and further distributed as per requirements.
Fire hydrate shall be provided. Fire alarms system, sprinkler, smoke detector and fire extinguisher shall be provided as required.
Retail shops are to be provided as part of commercial area to be sold separately by developers. Swimming pool, Gym , Spa shall be provided as the part of the club , Common Toilet, Guard Room.
Fire tender route and refused areas shall be provided. Emergencies Fire stairs shall be provided as approved by fire department drawings.
NIL
Showing 1 blocks with 87 units
Total Area
25047.62 m²
269610.08 ft²
Total Units
174
4 different types
Blocks & Floors
1
29 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
6440.00 m²
69319.52 ft²