| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 30 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 10 | 0 | 40 |
| Exp on Infrastructure and other structures | - | 0 | - | - |
| Expenses on Construction | 0 | 5 | 10 | - |
| Expenses on Infrastructure and other structure | 0 | - | - | 10 |
| Expenses on Infrastructure and othr structures | - | - | 0 | - |
| Expenses on construction | - | - | - | 20 |
| Other | 0 | 10 | 20 | 20 |
| Other cost including EDC Taxes Etc | 159 | - | - | 50 |
| Other cost including EDC and Taxes | - | 0 | - | - |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 8 | 30 | 60 | 100 |
| Sewerage treatment & garbage disposal | 0 | 20 | 20 | 40 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 20 | 20 |
| Water Supply System | 0 | 0 | 30 | 40 |
| other cost including EDC and Taxes | - | - | 50 | - |
Prima City is located in Rohtak.
Yes. Prima City is registered under RERA-PKL-1263-2023 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Prima City is 28 March 2025.