Showing 2 blocks with 14 units
Total Carpet Area
2185.92 m²
23529.02 ft²
Total Units
96
1 different types
Blocks & Floors
2
7 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
12390.00 m²
133364.72 ft²
Asper approved Layout Plan
Not Provided
Granular Sub Base with graded Stone Ballast 12.50cm thick, Wet Mix Macadam 10.00cm thick G S B 4.00cm thick BM and 2.5cm thick Bituminous Concrete
Not Provided
Water Supply distribution System through Sectorial O.H.T. PVC Pipes 110mm outer dia, 6Kg per sqcm as per design
250mm dia NP-2 RCC Hume Pipe laid with manhole and sewer connecting chamber which shall be connected with trunk sewer line already laid along 45m road as shown in Layout Plan
Drain section 20cm x 18cm provided by brick work in proportional 1 times cement and 6 times coarse sand mortar with struck and flush pointing
Not Provided
Not Provided
11 KV HT line Steel Tubular Pole SP 55, 11m long, LT Lines PCC Pole 8.5m long, Street Lighting on 7.5m/9m height Octagonal Pole Street Light connected with 33/11 KV Sub Station already running at Sector-3, Jagriti Vihar (Ext.), Meerut
Not Provided
Sewer line shall be connected in Sewerage treatment plan already running along 45m wide road as shown in Layout Plan
Not Provided
Not Provided
Not Provided
Fire Extinguisher ISI marked 4Kg and 6Kg capacity, CO2 Type fire extinguisher ISI marked 2Kg and 4Kg capacity with fire hose cabinet box of 18 gauge shall be provided