Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | - | 0 |
| Electricity Supply System | - | - | - | 0 |
| Other | - | - | - | 16.7 |
| Parks and Playgrounds | - | - | - | 0 |
| Roads & Pavements | - | - | - | 31.8 |
| Sewerage treatment & garbage disposal | - | - | - | 15.9 |
| Shopping area | - | - | - | 0 |
| Storm Water Drainage | - | - | - | 0 |
| Street Light | - | - | - | - |
| Water Supply System | - | - | - | 16.7 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 37.75 | 37.75 |
| Other | 16.7 | 16.7 | 16.7 | 16.7 |
| Parks and Playgrounds | 0 | 27.5 | 28.171875 | 0 |
| Roads & Pavements | 79.5 | 79.5 | 31.8 | 31.8 |
| Sewerage treatment & garbage disposal | 15.9 | 39.75 | 39.75 | 15.9 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 6.2 | 6.2 | 6.2 |
| Street Light | - | - | - | - |
| Water Supply System | 16.7 | 41.75 | 41.75 | 16.7 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 37.75 | 37.859375 | 0 | 0 |
| Other | 16.7 | 16.7 | 16.7 | 33.415625 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 31.8 | 31.925 | 0 | 0 |
| Sewerage treatment & garbage disposal | 15.9 | 15.9625 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3.1 | 3.1 | 3.1 | 3.9125 |
| Street Light | - | - | - | 10 |
| Water Supply System | 16.7 | 16.715625 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | - | - |
| Electricity Supply System | 0 | - | - | - |
| Other | 0 | - | - | - |
| Parks and Playgrounds | 0 | - | - | - |
| Roads & Pavements | 0 | - | - | - |
| Sewerage treatment & garbage disposal | 0 | - | - | - |
| Shopping area | 0 | - | - | - |
| Storm Water Drainage | 0 | - | - | - |
| Street Light | 5.90625 | - | - | - |
| Water Supply System | 0 | - | - | - |
Park City is located in Sirsa.
Yes. Park City is registered under RERA-PKL-1141-2022 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Park City is 31 December 2025.
Park City is developed by MONSOON BUILDWELL (P) LTD..