Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | 0 | 0 |
| Electricity Supply System | - | - | 6.05 | 6.05 |
| Other | - | - | 0.7 | 0.7 |
| Parks and Playgrounds | - | - | 1.63 | 1.63 |
| Roads & Pavements | - | - | 5.12 | 5.12 |
| Sewerage treatment & garbage disposal | - | - | 2.79 | 2.79 |
| Shopping area | - | - | 0 | 0 |
| Storm Water Drainage | - | - | 3.26 | 3.26 |
| Water Supply System | - | - | 3.72 | 3.72 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 6.05 | 6.05 | 6.05 | 6.05 |
| Other | 0.7 | 0.7 | 0.7 | 0.7 |
| Parks and Playgrounds | 1.63 | 1.63 | 1.63 | 1.63 |
| Roads & Pavements | 5.12 | 5.12 | 5.12 | 5.12 |
| Sewerage treatment & garbage disposal | 2.79 | 2.79 | 2.79 | 2.79 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3.26 | 3.26 | 3.26 | 3.26 |
| Water Supply System | 3.72 | 3.72 | 3.72 | 3.72 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 6.05 | 6.05 | 6.05 | 6.05 |
| Other | 0.7 | 0.7 | 0.7 | 0.7 |
| Parks and Playgrounds | 1.63 | 1.63 | 1.63 | 1.63 |
| Roads & Pavements | 5.12 | 5.12 | 5.12 | 5.12 |
| Sewerage treatment & garbage disposal | 2.79 | 2.79 | 2.79 | 2.79 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3.26 | 3.26 | 3.26 | 3.26 |
| Water Supply System | 3.72 | 3.72 | 3.72 | 3.72 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 6.05 | 6.05 | 6.05 | 6.05 |
| Other | 0.7 | 0.7 | 0.7 | 0.7 |
| Parks and Playgrounds | 1.63 | 1.63 | 1.63 | 1.63 |
| Roads & Pavements | 5.12 | 5.12 | 5.12 | 5.12 |
| Sewerage treatment & garbage disposal | 2.79 | 2.79 | 2.79 | 2.79 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3.26 | 3.26 | 3.26 | 3.26 |
| Water Supply System | 3.72 | 3.72 | 3.72 | 3.72 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 6.05 | 6.05 | 6.05 | 6.05 |
| Other | 0.7 | 0.7 | 0.7 | 0.7 |
| Parks and Playgrounds | 1.63 | 1.63 | 1.63 | 1.63 |
| Roads & Pavements | 5.12 | 5.12 | 5.12 | 5.12 |
| Sewerage treatment & garbage disposal | 2.79 | 2.79 | 2.79 | 2.79 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3.26 | 3.26 | 3.25 | 3.26 |
| Water Supply System | 3.72 | 3.72 | 3.72 | 3.72 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | - | - |
| Electricity Supply System | 6.05 | 6.05 | - | - |
| Other | 0.7 | 0.7 | - | - |
| Parks and Playgrounds | 1.63 | 1.63 | - | - |
| Roads & Pavements | 5.12 | 5.12 | - | - |
| Sewerage treatment & garbage disposal | 2.79 | 2.79 | - | - |
| Shopping area | 0 | 0 | - | - |
| Storm Water Drainage | 3.26 | 3.26 | - | - |
| Water Supply System | 3.72 | 3.72 | - | - |