Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | 0 | 0 | - |
| Electricity Supply System | - | 0 | 14 | - |
| Other | - | 2.35 | 0 | - |
| Parks and Playgrounds | - | 0 | 0 | - |
| Roads & Pavements | - | 4.6 | 4.6 | - |
| Sewerage treatment & garbage disposal | - | 18.4 | 12.1 | - |
| Shopping area | - | 0 | 0 | - |
| Storm Water Drainage | - | 15.5 | 15.79 | - |
| Water Supply System | - | 0 | 30.6 | - |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | - |
| Electricity Supply System | 8.8 | 0 | 0 | - |
| Other | 0 | 0 | 0 | - |
| Parks and Playgrounds | 0 | 2.7 | 0 | - |
| Roads & Pavements | 28.2 | 23.91 | 4.6 | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | - |
| Shopping area | 0 | 0 | 0 | - |
| Storm Water Drainage | 0 | 0 | 0 | - |
| Water Supply System | 52.87 | 0 | 0 | - |