Uploaded on: 28-07-2022
Uploaded on: 28-07-2022



Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall Gate and Guard Room | - | - | 10 | 20 |
| Clubhouse/community centres | - | 0 | 0 | 0 |
| Electricity Supply System | - | 0 | 0 | 18 |
| Other | - | 0 | 7.5 | 7.5 |
| Parks and Playgrounds | - | 0 | 0 | 0 |
| Roads & Pavements | - | 0 | 10 | 40 |
| Sewerage treatment & garbage disposal | - | 0 | 0 | 100 |
| Shopping area | - | 0 | 0 | 0 |
| Storm Water Drainage | - | 0 | 5 | 13 |
| Water Supply System | - | 0 | 15 | 17 |
Developed by
7 Projects
EXECUTIVE SUMMARY Mapsko Group is a mid-sized, unlisted real estate developer headquartered in Gurugram, Haryana, operating under the primary legal entity Mapsko Builders Private Limited (MBPL). The group traces its root…