| Particulars | Expenditure (in Lakhs) |
|---|---|
| STP | 0 |
| Other | 270 |
| Parking | 5 |
| Street Light | 10 |
| Shopping area | 0 |
| Renewable Energy | 4 |
| Roads & Pavements | 33 |
| Electric sub tation | 85 |
| Water Supply System | 57.85 |
| Storm Water Drainage | 1.32 |
| Parks and Playgrounds | 0 |
| Rain Water Harvesting | 0 |
| Security Fire Fighting | 167 |
| Underground water tank | 9 |
| Electricity Supply System | 37.55 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | - | 0 |
| Electric sub tation | - | - | - | - |
| Electrical Sub Station | - | - | - | 0.06 |
| Electricity Supply System | - | - | - | 50.73 |
| Other | - | - | - | 0.8 |
| Parking | - | - | - | - |
| Parks and Playgrounds | - | - | - | 0 |
| Rain Water Harvesting | - | - | - | - |
| Rain water harvesting | - | - | - | - |
| Renewable Energy | - | - | - | - |
| Renewable energy | - | - | - | - |
| Roads & Pavements | - | - | - | 0 |
| STP | - | - | - | - |
| Security Fire Fighting | - | - | - | - |
| Security ire Fighting | - | - | - | - |
| Security Fire Fighting | - | - | - | - |
| Security and Fire Fighting | - | - | - | 12.14 |
| Sewerage treatment & garbage disposal | - | - | - | 0 |
| Shopping area | - | - | - | 0 |
| Storm Water Drainage | - | - | - | 2.95 |
| Street Light | - | - | - | - |
| Street Lighting | - | - | - | 4.84 |
| UGT | - | - | - | 0.23 |
| Underground water tank | - | - | - | - |
| Water Supply System | - | - | - | 2.65 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electric sub tation | 43.66 | 52.39 | 52.39 | 52.39 |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | 23.42 | 11.71 | 11.71 | 11.71 |
| Other | 75.74 | 75.74 | 75.74 | 94.68 |
| Parking | 13.84 | 16.6 | 19.37 | 22.14 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | 0.31 | 0.37 | 0.43 | 0.5 |
| Rain water harvesting | - | - | - | - |
| Renewable Energy | 3.9 | - | - | 3.9 |
| Renewable energy | - | 3.9 | 3.9 | - |
| Roads & Pavements | 6.73 | 6.73 | 8.41 | 8.41 |
| STP | - | - | - | - |
| Security Fire Fighting | 15.36 | 15.36 | 15.36 | 15.36 |
| Security ire Fighting | - | - | - | - |
| Security Fire Fighting | - | - | - | - |
| Security and Fire Fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0.8 | 0.8 | 0.8 | 0.8 |
| Street Light | 3.8 | 3.8 | 3.8 | 3.8 |
| Street Lighting | - | - | - | - |
| UGT | - | - | - | - |
| Underground water tank | 1.08 | 1.08 | 1.08 | 1.08 |
| Water Supply System | 5.11 | 5.11 | 5.11 | 5.11 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electric sub tation | 52.39 | 52.39 | 52.39 | 52.39 |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | 11.71 | 11.71 | 7.03 | 7.03 |
| Other | 113.62 | 151.49 | 151.49 | 151.49 |
| Parking | 22.14 | 22.14 | 22.14 | 22.14 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | 0.5 | 0.5 | 0.5 | - |
| Rain water harvesting | - | - | - | 0.5 |
| Renewable Energy | - | - | - | - |
| Renewable energy | 3.9 | 3.9 | 3.9 | 4.55 |
| Roads & Pavements | 8.41 | 8.41 | 8.41 | 8.41 |
| STP | - | - | - | - |
| Security Fire Fighting | 15.36 | 15.36 | - | 15.36 |
| Security ire Fighting | - | - | 15.36 | - |
| Security Fire Fighting | - | - | - | - |
| Security and Fire Fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0.8 | 0.8 | 0.8 | 0.84 |
| Street Light | 3.8 | 3.8 | 2.17 | 2.17 |
| Street Lighting | - | - | - | - |
| UGT | - | - | - | - |
| Underground water tank | 1.08 | 1.35 | 1.35 | 1.35 |
| Water Supply System | 5.11 | 5.11 | 6.08 | 10.22 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electric sub tation | 52.39 | 52.39 | 52.39 | 44.36 |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | 7.03 | 7.03 | 7.03 | 7.03 |
| Other | 151.49 | 113.62 | 113.62 | 113.62 |
| Parking | 22.14 | 20.28 | 19.37 | 19.37 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | 0.5 | 0.5 | 0.5 | 0.43 |
| Rain water harvesting | - | - | - | - |
| Renewable Energy | - | - | - | - |
| Renewable energy | 4.55 | 4.55 | 4.55 | 4.55 |
| Roads & Pavements | 12.04 | 11.77 | 11.77 | 10.09 |
| STP | - | - | - | 8.8 |
| Security Fire Fighting | - | 19.2 | 16.09 | 7.68 |
| Security ire Fighting | - | - | - | - |
| Security Fire Fighting | 17.2 | - | - | - |
| Security and Fire Fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 1.12 | 1.12 | 1.12 | 0.98 |
| Street Light | 1.63 | 1.63 | 1.63 | 1.63 |
| Street Lighting | - | - | - | - |
| UGT | - | - | - | - |
| Underground water tank | 1.35 | 1.35 | 1.35 | 1.35 |
| Water Supply System | 10.22 | 10.22 | 10.22 | 10.22 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electric sub tation | 43.66 | 43.66 | 34.93 | 34.93 |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | 7.03 | 7.03 | 3.04 | 2.34 |
| Other | 96.39 | 56.81 | 37.87 | 30.49 |
| Parking | 16.6 | 12.65 | 0.8 | - |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | 0.37 | 0.31 | - | - |
| Rain water harvesting | - | - | - | - |
| Renewable Energy | - | - | - | - |
| Renewable energy | 4.55 | 4.55 | 0.65 | 0.65 |
| Roads & Pavements | 10.09 | 8.41 | 3.36 | 2.05 |
| STP | 11.74 | 8.8 | - | - |
| Security Fire Fighting | 7.68 | 7.68 | - | - |
| Security ire Fighting | - | - | - | - |
| Security Fire Fighting | - | - | - | - |
| Security and Fire Fighting | - | - | 6.45 | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0.48 | 0.48 | 0 | 0 |
| Street Light | 1.63 | 1.63 | 1.63 | 1.21 |
| Street Lighting | - | - | - | - |
| UGT | - | - | 0.25 | - |
| Underground water tank | 1.35 | 1.35 | - | - |
| Water Supply System | 6.81 | 6.81 | 3.41 | 3.27 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | - | - |
| Electric sub tation | 19.04 | - | - | - |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | 2.34 | - | - | - |
| Other | 18.94 | - | - | - |
| Parking | - | - | - | - |
| Parks and Playgrounds | 0 | - | - | - |
| Rain Water Harvesting | - | - | - | - |
| Rain water harvesting | - | - | - | - |
| Renewable Energy | - | - | - | - |
| Renewable energy | 0.55 | - | - | - |
| Roads & Pavements | 1.68 | - | - | - |
| STP | - | - | - | - |
| Security Fire Fighting | - | - | - | - |
| Security ire Fighting | - | - | - | - |
| Security Fire Fighting | - | - | - | - |
| Security and Fire Fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | - | - | - |
| Shopping area | 0 | - | - | - |
| Storm Water Drainage | 0 | - | - | - |
| Street Light | 0.54 | - | - | - |
| Street Lighting | - | - | - | - |
| UGT | - | - | - | - |
| Underground water tank | - | - | - | - |
| Water Supply System | 1.7 | - | - | - |
M3m Urbana Premium is located in Gurgaon.
Yes. M3m Urbana Premium is registered under RERA-GRG-604-2020 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for M3m Urbana Premium is 28 August 2024.
M3m Urbana Premium is developed by MARTIAL BUILDCON PVT. LTD. M3M INDIA PVT. LTD..
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.