| Particulars | Expenditure (in Lakhs) |
|---|---|
| STP | 45 |
| Other | 0 |
| Parking | 127.58 |
| Street Light | 18.59 |
| Shopping area | 0 |
| Roads & Pavements | 243.08 |
| Water Supply System | 259.72 |
| Storm Water Drainage | 47.73 |
| Electrical Substation | 1152.22 |
| Parks and Playgrounds | 13.35 |
| Rain water harvesting | 19.45 |
| Under ground water tank | 28.32 |
| Electricity Supply System | 37.39 |
| Security and Fire fighting | 184.7 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 84.85 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | 0 | 0 |
| Electrical sub station | - | - | - | - |
| Electricity Supply System | - | - | 0 | 0 |
| Other | - | - | 0 | 0 |
| Parking | - | - | - | - |
| Parks and Playgrounds | - | - | 0 | 0 |
| Roads & Pavements | - | - | 0 | 0 |
| Security and Firefighting | - | - | - | - |
| Sewerage treatment & garbage disposal | - | - | 0 | 0 |
| Shopping area | - | - | 0 | 0 |
| Storm Water Drainage | - | - | 0 | 0 |
| Water Supply System | - | - | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical sub station | - | 177.88 | 177.88 | 177.88 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 0 | 51.09 | 51.09 | 51.09 |
| Parking | - | 28.88 | 49.5 | 82.5 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Security and Firefighting | 0 | 24.36 | 26.8 | 7.74 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical sub station | 92.95 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 51.09 | 0 | 0 | 0 |
| Parking | 61.88 | 62.17 | - | - |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Security and Firefighting | 11.78 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical sub station | - | - | - | - |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parking | - | - | - | - |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Security and Firefighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Water Supply System | 0 | 0 | 0 | 0 |
M3M International Financial Center is located in Sector 66, Gurgaon. The project is spread across 4.84 acres.
Yes. M3M International Financial Center is registered under RERA-GRG-809-2021 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for M3M International Financial Center is 31 December 2024.
M3M International Financial Center is developed by M3M.
M3M International Financial Center comprises 1 towers.
Developed by
41 Projects
EXECUTIVE SUMMARY OF M3M M3M India Private Limited is a privately held real estate developer incorporated in March 2007 and headquartered in Gurugram, Haryana. The company was founded by Basant Bansal, with Roop Bansal a…
Know More about M3M