Launch Date
Completion Date
RERA ID
28.726080
77.751450
Demarcation of plot with 230 toe wall There is dowel entry in entrance 2 side open
Boundary wall designed with brick work and RCC column and beam as per design with 230 mm toe wall
road work with paver block suggested by Architect
all work with narrow footpaths with paver block
water supply including drinking water facilitys after treatment will be pumped from ug to oth
sewer system with dwc hdpe or equivalent pipe shall be connected to authority disposal line
saucer drain RCC NP2 or equivalent pipe shall be connected to Rain water harvesting pits and over flow to authority drainage system
na
Plantation will be done as per applicable norms to maintain for greenery and pollution free atmosfear the tree wiil be planted surrounding the plot
design for electrict supply including street lighting under ground electric supply provided with PVC conduct as per electrical layout map continuous gererator backup
na
Treatment and disposal system of sewage and sullage water to be connected in enternal sewerage
collection disposal through authorized vender
rain water harvesting to be provided
na
na
na
staircases are provide on 2 side of plots as per architect
na
Showing 1 blocks with 4 units
Total Carpet Area
17593.43 m²
189373.92 ft²
Total Units
61
1 different types
Blocks & Floors
1
4 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
815.50 m²
8777.96 ft²