26.70908
83.41076
Total Units
44
2 unit types
Carpet Area
28,173 ft²
2,617.34 m² · carpet only, excludes balcony
Blocks & Floors
3
11 floors across all blocks
Parking
0
0 garages, 0 open
Average carpet area 640 ft² (59.48 m²)Balconies 24Parking per unit 0.00
All blocks
Showing 14 of 14 rows · 7 of 12 columns
| Block | Floor | Type | Units | Carpet Areaper unit | Balconies | Balcony Areatotal |
|---|---|---|---|---|---|---|
| 1 | GF | OTHER | 2 | 185 ft²17.23 m² | — | — |
| 1 | GF | OTHER | 2 | 195 ft²18.14 m² | — | — |
| 1 | 1 | 3 BHK | 4 | 809 ft²75.16 m² | 3 | 119 ft²11.10 m² |
| 1 | 3 | 3 BHK | 4 | 809 ft²75.16 m² | 3 | 119 ft²11.10 m² |
| 2 | GF | OTHER | 2 | 185 ft²17.23 m² | — | — |
| 2 | GF | OTHER | 2 | 195 ft²18.14 m² | — | — |
| 2 | 1 | 3 BHK | 4 | 809 ft²75.16 m² | 3 | 119 ft²11.10 m² |
| 2 | 2 | 3 BHK | 4 | 809 ft²75.16 m² | 3 | 119 ft²11.10 m² |
| 2 | 3 | 3 BHK | 4 | 809 ft²75.16 m² | 3 | 119 ft²11.10 m² |
| 3 | GF | OTHER | 2 | 185 ft²17.23 m² | — | — |
| 3 | GF | OTHER | 2 | 195 ft²18.14 m² | — | — |
| 3 | 1 | 3 BHK | 4 | 809 ft²75.16 m² | 3 | 119 ft²11.10 m² |
| 3 | 2 | 3 BHK | 4 | 809 ft²75.16 m² | 3 | 119 ft²11.10 m² |
| 3 | 3 | 3 BHK | 4 | 809 ft²75.16 m² | 3 | 119 ft²11.10 m² |
Blocks have been demarcated at site and work is in progress
boundary wall has been constructed at site
Bituminous roads has been proposed. Trunk roads construction work is in progress. Link roads will be constructed after the construction of blocks
footpaths have been provisioned and shall be constructed after the construction of blocks
Trunk water supply lines for feeding these blocks are being laid.
Trunk lines are being laid at site. sewer lines will be laid at the end of construction of blocks
R.C.C. Trunk drains construction work is going on at site. Once the construction of blocks is over these lines shall be connected to the system
n/a
Plantation shall be taken up after the construction of blocks and development of site
Electrical load as per UPPCL shall be sanctioned, installed, and shall be handed over to UPPCL for maintenance
N/A
Primary treatment at block level through STP, secondary treatment proposed at STP
garbage collection centre proposed at site
N/A
N/A
N/A
N/A
N/A
N/A
Lohia Enclave - Phase - Iii is located in Gorakhpur.
Yes. Lohia Enclave - Phase - Iii is registered under UPRERAPRJ9518 with the Uttar Pradesh RERA (UP-RERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Lohia Enclave - Phase - Iii is 30 May 2022.
Lohia Enclave - Phase - Iii is developed by GORAKHPUR DEVELOPMENT AUTHORITY.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.