| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 25 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 50.2 | - | - | - |
| Electricity Supply System | 29.82 | - | - | - |
| Other | 0 | - | - | - |
| Parks and Playgrounds | 10.07 | - | - | - |
| Roads & Pavements | 56.39 | - | - | - |
| Sewerage treatment & garbage disposal | 21.91 | - | - | - |
| Shopping area | 120 | - | - | - |
| Storm Water Drainage | 29.95 | - | - | - |
| Water Supply System | 27.67 | - | - | - |