Have queries on this Project?
Uploaded on: 19-02-2020
Uploaded on: 14-02-2020
Uploaded on: 14-02-2020




| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 86 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 98 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| CONSULTANCY | - | - | 10 | 10 |
| CONSULTANCY ETC | - | - | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Consultancy Fees Gate complex etc | - | 10 | - | - |
| Electricity Supply System | 0 | 50 | 50 | 50 |
| HORTICULTURE | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 50 | 50 | 50 |
| STREET LIGHT | - | - | 10 | - |
| STREET LIGHTING | - | - | - | 10 |
| Sewerage treatment & garbage disposal | 0 | 0 | 20 | 20 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 20 | 40 |
| Water Supply System | 0 | 0 | 20 | 40 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| CONSULTANCY | 10 | 20 | - | - |
| CONSULTANCY ETC | - | - | 20 | 10 |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Consultancy Fees Gate complex etc | - | - | - | - |
| Electricity Supply System | 0 | 0 | 100 | 100 |
| HORTICULTURE | - | 1 | 1 | 1 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 50 | 50 | 0 | 0 |
| STREET LIGHT | - | 10 | 16 | - |
| STREET LIGHTING | 10 | - | - | - |
| Sewerage treatment & garbage disposal | 20 | 40 | 20 | 40 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 20 | 40 | 20 | 40 |
| Water Supply System | 20 | 40 | 20 | 40 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| CONSULTANCY | - | - | - | - |
| CONSULTANCY ETC | 10 | 7 | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Consultancy Fees Gate complex etc | - | - | - | - |
| Electricity Supply System | 100 | 100 | 100 | 100 |
| HORTICULTURE | 1 | 1 | - | 1 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 50 | 50 | 50 |
| STREET LIGHT | - | - | - | - |
| STREET LIGHTING | - | - | - | - |
| Sewerage treatment & garbage disposal | 40 | 42 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 40 | 42 | 0 | 100 |
| Water Supply System | 40 | 42 | 50 | 50 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| CONSULTANCY | - | - | - | - |
| CONSULTANCY ETC | - | - | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Consultancy Fees Gate complex etc | - | - | - | - |
| Electricity Supply System | 100 | 0 | 0 | 0 |
| HORTICULTURE | 1 | 1 | 1 | - |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 50 | 50 | 100 | 100 |
| STREET LIGHT | - | - | - | - |
| STREET LIGHTING | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 11 | 0 | 0 | 0 |
| Water Supply System | 26 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| CONSULTANCY | - | - | - | - |
| CONSULTANCY ETC | - | - | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Consultancy Fees Gate complex etc | - | - | - | - |
| Electricity Supply System | 0 | 0 | 100 | 62 |
| HORTICULTURE | - | - | 4 | 1 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 100 | 100 | 21 | 0 |
| STREET LIGHT | - | - | - | - |
| STREET LIGHTING | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Water Supply System | 0 | 0 | 0 | 0 |
Industrial Project 66.081 Acres is located in Jhajjar.
Yes. Industrial Project 66.081 Acres is registered under RERA-PKL-813-2020 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Industrial Project 66.081 Acres is 11 February 2025.
Industrial Project 66.081 Acres is developed by MODEL ECONOMIC TOWNSHIP LIMITED.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.