Have queries on this Project?
Uploaded on: 15-04-2023
Uploaded on: 15-04-2023

| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | - | 0 |
| Electricity Supply System | - | - | - | 20 |
| External Electrification | - | - | - | - |
| Other | - | - | - | 2 |
| Parks and Playgrounds | - | - | - | 15 |
| Roads & Pavements | - | - | - | 52 |
| STP | - | - | - | 0 |
| Sewerage treatment & garbage disposal | - | - | - | 24 |
| Shopping area | - | - | - | 0 |
| Storm Water Drainage | - | - | - | 0 |
| U G Tank | - | - | - | 24 |
| Water Supply System | - | - | - | 17 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | 0 | 0 | 0 |
| Electricity Supply System | - | 60 | 40 | 30 |
| External Electrification | - | - | 75 | 75 |
| Other | - | 4 | 12 | 14 |
| Parks and Playgrounds | - | 15 | 0 | 0 |
| Roads & Pavements | - | 26 | 52 | 52 |
| STP | - | 0 | - | - |
| Sewerage treatment & garbage disposal | - | 72 | 15 | 15 |
| Shopping area | - | 0 | 0 | 0 |
| Storm Water Drainage | - | 25 | 25 | 25 |
| U G Tank | - | 32 | - | - |
| Water Supply System | - | 51 | 0 | 0 |
Gulmohar is located in Faridabad.
Yes. Gulmohar is registered under RERA-PKL-1264-2023 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Gulmohar is 9 April 2028.
Gulmohar is developed by EMARALD INFRALAND LLP.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.