Demarcation of plots has been completed by authorized surveyor
Boundary wall construction is under process as per the drawings about nine inches thickness with gate
RCC road will be constructed as per the drawings at approx 7.5 meter wide.
Footpath will be constructed around the plot as per the drawings at approx 1.5-2 meter
Water supply will be provided by ground water source through pipeline / storage tanks in apartments.
STP System will be maintained as per the drawings and sewerage disposal will be connected through municipal line
Drain will be constructed as per the drawings in and around the whole area.
N/A
Plantation will be done after completion of main building towers.
Electricity supply will be provided as per the drawings and includes street lighting.
Multipurpose Hall, Sports area etc. will be provided as per the drawings.
Sewerage disposal system will be done through the municipal line of sewer.
Solid waste management and disposal will be provided through any registered agency.
Will be done by harvesting pit system
Will be done as per the requirement.
Fire Stairs and other fire prevention system will be installed as per the government norms. Fire NOC attached
Swimming pool and other green area will be developed as per the drawings.
Fire stairs and other fire safety services will be provided.
Other services like swimming pool etc will be developed as per the drawings.
Showing 2 blocks with 92 units
Total Carpet Area
19172.62 m²
206372.16 ft²
Total Units
172
3 different types
Blocks & Floors
2
25 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
8130.00 m²
87510.51 ft²