Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | 0 | 0 | 0 |
| Electricity Supply System | - | 11.84 | 11.84 | 11.84 |
| Other | - | 2.84 | 2.84 | 2.84 |
| Parks and Playgrounds | - | 5.68 | 5.68 | 5.68 |
| Roads & Pavements | - | 12.78 | 12.78 | 12.78 |
| Sewerage treatment & garbage disposal | - | 4.74 | 4.74 | 4.74 |
| Shopping area | - | 0 | 0 | 0 |
| Storm Water Drainage | - | 4.74 | 4.74 | 4.74 |
| Water Supply System | - | 4.74 | 4.74 | 4.74 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 11.84 | 11.84 | 11.84 | 11.84 |
| Other | 2.84 | 2.84 | 2.84 | 2.84 |
| Parks and Playgrounds | 5.68 | 5.68 | 5.68 | 5.68 |
| Roads & Pavements | 12.78 | 12.78 | 12.78 | 12.78 |
| Sewerage treatment & garbage disposal | 4.74 | 4.74 | 4.74 | 4.74 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 4.74 | 4.74 | 4.74 | 4.74 |
| Water Supply System | 4.74 | 4.74 | 4.74 | 4.74 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 11.84 | 11.84 | 11.84 | 11.84 |
| Other | 2.84 | 2.84 | 2.84 | 2.84 |
| Parks and Playgrounds | 5.68 | 5.68 | 5.68 | 5.68 |
| Roads & Pavements | 12.78 | 12.78 | 12.78 | 12.78 |
| Sewerage treatment & garbage disposal | 4.74 | 4.74 | 4.74 | 4.74 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 4.74 | 4.74 | 4.74 | 4.74 |
| Water Supply System | 4.74 | 4.74 | 4.74 | 4.74 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 11.84 | 11.84 | 11.84 | 11.84 |
| Other | 2.84 | 2.84 | 2.84 | 2.84 |
| Parks and Playgrounds | 5.68 | 5.68 | 5.68 | 5.68 |
| Roads & Pavements | 12.78 | 12.78 | 12.78 | 12.78 |
| Sewerage treatment & garbage disposal | 4.74 | 4.74 | 4.74 | 4.74 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 4.74 | 4.74 | 4.74 | 4.74 |
| Water Supply System | 4.74 | 4.74 | 4.74 | 4.74 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 11.84 | 11.84 | 11.84 | 11.84 |
| Other | 2.84 | 2.84 | 2.84 | 2.84 |
| Parks and Playgrounds | 5.68 | 5.68 | 5.68 | 5.68 |
| Roads & Pavements | 12.78 | 12.78 | 12.78 | 12.78 |
| Sewerage treatment & garbage disposal | 4.74 | 4.74 | 4.74 | 4.74 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 4.74 | 4.74 | 4.74 | 4.74 |
| Water Supply System | 4.74 | 4.74 | 4.74 | 4.74 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | - | - |
| Electricity Supply System | 11.84 | - | - | - |
| Other | 2.84 | - | - | - |
| Parks and Playgrounds | 5.68 | - | - | - |
| Roads & Pavements | 12.78 | - | - | - |
| Sewerage treatment & garbage disposal | 4.74 | - | - | - |
| Shopping area | 0 | - | - | - |
| Storm Water Drainage | 4.74 | - | - | - |
| Water Supply System | 4.74 | - | - | - |
Globus Industrial Township is located in Sonipat.
Yes. Globus Industrial Township is registered under RERA-PKL-1241-2023 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Globus Industrial Township is 1 March 2028.
Globus Industrial Township is developed by Y P INFRATECH PRIVATE LIMITED.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.