| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 442.65 |
| Shopping area | 0 |
| Roads & Pavements | 328 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 14.38 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 132 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 152 | 150 | 152 |
| Electricity Supply System | 111.5 | 272.13 | 86.98 | 51.1 |
| Other | 117.06 | 10.68 | 62.55 | 65.55 |
| Parks and Playgrounds | 0 | 36.72 | 36.72 | 36.72 |
| Roads & Pavements | 0 | 0 | 0 | 253.35 |
| Sewerage treatment & garbage disposal | 159.12 | 211.62 | 159.12 | 103.44 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 96 | 96.06 | 96.06 | 32.02 |
| Water Supply System | 98.23 | 115.34 | 98.23 | 63.76 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 152 | 152 | - | - |
| Electricity Supply System | 181.92 | 195.16 | - | - |
| Other | 35.31 | 0 | - | - |
| Parks and Playgrounds | 36.72 | 36.72 | - | - |
| Roads & Pavements | 226.77 | 196.27 | - | - |
| Sewerage treatment & garbage disposal | 75.6 | 57.56 | - | - |
| Shopping area | 0 | 0 | - | - |
| Storm Water Drainage | 0 | 0 | - | - |
| Water Supply System | 46.53 | 17.1 | - | - |
Ferrous Megapolis City Phase 1 is located in Faridabad.
Yes. Ferrous Megapolis City Phase 1 is registered under RERA-PKL-1147-2022 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Ferrous Megapolis City Phase 1 is 2 January 2025.
Ferrous Megapolis City Phase 1 is developed by FERROUS TOWNSHIP PVT. LTD..
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.