| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electical Panels | - | - | - | - |
| Electrical Substation | - | - | - | - |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Miscellaneous Works | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Others including Contingencies and GST and LC | 0 | 0 | 0 | 0.6 |
| Parking | - | - | - | - |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | - | - | - | - |
| Roads & Pavements | 0 | 0 | 0 | 0.4 |
| STP | - | - | - | - |
| Security Fire fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 1 |
| Shopping area | 0 | 0 | 0 | 0 |
| Signages Plot Demarcation | - | - | - | - |
| Storm Water Drainage | 0 | 0 | 0 | 1.4 |
| Street light | - | - | - | - |
| Switching Station Works | - | - | - | - |
| UGT | - | - | - | - |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electical Panels | - | - | - | - |
| Electrical Substation | - | - | - | - |
| Electricity Supply System | 0 | 0 | 1.5 | 3.7 |
| Miscellaneous Works | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Others including Contingencies and GST and LC | 1 | 2.5 | 4.4 | 7.5 |
| Parking | - | - | - | - |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | - | - | - | - |
| Roads & Pavements | 0.8 | 0.4 | 0 | 1.5 |
| STP | - | - | - | - |
| Security Fire fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 1.5 | 4.1 | 6.2 | 9.3 |
| Shopping area | 0 | 0 | 0 | 0 |
| Signages Plot Demarcation | - | - | - | - |
| Storm Water Drainage | 2.1 | 5.6 | 8.4 | 12.6 |
| Street light | - | - | - | - |
| Switching Station Works | - | - | - | - |
| UGT | - | - | - | - |
| Water Supply System | 0 | 0 | 1.3 | 3.3 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electical Panels | - | - | - | - |
| Electrical Substation | 0 | 0 | 13 | 31.4 |
| Electricity Supply System | 8.1 | 11.8 | 16.2 | 14 |
| Miscellaneous Works | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Others including Contingencies and GST and LC | 17.3 | 27.5 | 37.6 | 46.3 |
| Parking | - | - | - | - |
| Parks and Playgrounds | 0 | 0 | 0 | 7.5 |
| Rain Water Harvesting | - | - | - | - |
| Roads & Pavements | 7.6 | 9.8 | 14.3 | 14.3 |
| STP | 6.8 | 16.5 | 12.3 | 8.9 |
| Security Fire fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 9.3 | 7.2 | 5.1 | 3.6 |
| Shopping area | 0 | 0 | 0 | 0 |
| Signages Plot Demarcation | - | - | - | - |
| Storm Water Drainage | 12.6 | 9.8 | 7 | 4.9 |
| Street light | - | - | - | - |
| Switching Station Works | 9.7 | 24.3 | 53.4 | 77.7 |
| UGT | 8.1 | 19.8 | 14.8 | 10.7 |
| Water Supply System | 7.3 | 10.6 | 14.5 | 12.6 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electical Panels | 5.8 | 57.8 | 46.2 | 5.8 |
| Electrical Substation | 36.8 | 23.8 | 3.3 | 0 |
| Electricity Supply System | 9.6 | 5.9 | 3 | 0 |
| Miscellaneous Works | 6.4 | 64.3 | 51.5 | 6.4 |
| Other | 0 | 0 | 0 | 0 |
| Others including Contingencies and GST and LC | 61.6 | 87.8 | 63.3 | 26.4 |
| Parking | 0 | 3.6 | 5.6 | 2.8 |
| Parks and Playgrounds | 35.3 | 53.4 | 39.8 | 17 |
| Rain Water Harvesting | 0 | 2 | 3.1 | 1.5 |
| Roads & Pavements | 10.6 | 7.6 | 4.5 | 3.8 |
| STP | 9.5 | 9.6 | 6.2 | 0.8 |
| Security Fire fighting | 0 | 0.8 | 1.2 | 0.6 |
| Sewerage treatment & garbage disposal | 2.6 | 1.5 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Signages Plot Demarcation | 0 | 4.6 | 7.3 | 3.6 |
| Storm Water Drainage | 3.5 | 2.1 | 0 | 0 |
| Street light | 0 | 5.6 | 8.7 | 4.3 |
| Switching Station Works | 106.8 | 92.2 | 63.1 | 58.3 |
| UGT | 11.4 | 11.5 | 7.5 | 1 |
| Water Supply System | 8.6 | 5.3 | 2.6 | 0 |