Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | - | 0 |
| Electricity Supply System | - | - | - | 6 |
| Other | - | - | - | 0 |
| Parks and Playgrounds | - | - | - | 3.25 |
| Roads & Pavements | - | - | - | 5.75 |
| Sewerage treatment & garbage disposal | - | - | - | 3.75 |
| Shopping area | - | - | - | 0 |
| Storm Water Drainage | - | - | - | 3 |
| Water Supply System | - | - | - | 3.25 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 6 | 6 | 6 | 6 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 3.25 | 3.25 | 3.25 | 3.25 |
| Roads & Pavements | 5.75 | 5.75 | 5.75 | 5.75 |
| Sewerage treatment & garbage disposal | 3.75 | 3.75 | 3.75 | 3.75 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3 | 3 | 3 | 3 |
| Water Supply System | 3.25 | 3.25 | 3.25 | 3.25 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 6 | 6 | 6 | 6 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 3.25 | 3.25 | 3.25 | 3.25 |
| Roads & Pavements | 5.75 | 5.75 | 5.75 | 5.75 |
| Sewerage treatment & garbage disposal | 3.75 | 3.75 | 3.75 | 3.75 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3 | 3 | 3 | 3 |
| Water Supply System | 3.25 | 3.25 | 3.25 | 3.25 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 6 | 6 | 6 | 6 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 3.25 | 3.25 | 3.25 | 3.25 |
| Roads & Pavements | 5.75 | 5.75 | 5.75 | 5.75 |
| Sewerage treatment & garbage disposal | 3.75 | 3.75 | 3.75 | 3.75 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3 | 3 | 3 | 3 |
| Water Supply System | 3.25 | 3.25 | 3.25 | 3.25 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 6 | 6 | 6 | 6 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 3.25 | 3.25 | 3.25 | 3.25 |
| Roads & Pavements | 5.75 | 5.75 | 5.75 | 5.75 |
| Sewerage treatment & garbage disposal | 3.75 | 3.75 | 3.75 | 3.75 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3 | 3 | 3 | 3 |
| Water Supply System | 3.25 | 3.25 | 3.25 | 3.25 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 6 | 6 | 6 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 3.25 | 3.25 | 3.25 | 0 |
| Roads & Pavements | 5.75 | 5.75 | 5.75 | 0 |
| Sewerage treatment & garbage disposal | 3.75 | 3.75 | 3.75 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3 | 3 | 3 | 0 |
| Water Supply System | 3.25 | 3.25 | 3.25 | 0 |
Elite Homes is located in Jhajjar.
Yes. Elite Homes is registered under RERA-PKL-1373-2023 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Elite Homes is 16 January 2028.
Elite Homes is developed by Y P INFRATECH PVT. LTD..