Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | 0 | 0 | 0 |
| Electricity Supply System | - | 16.23 | 16.23 | 16.23 |
| Other | - | 1.95 | 1.95 | 1.95 |
| Parks and Playgrounds | - | 3.26 | 3.26 | 3.26 |
| Roads & Pavements | - | 11.69 | 11.69 | 11.69 |
| Sewerage treatment & garbage disposal | - | 14.29 | 14.29 | 14.29 |
| Shopping area | - | 0 | 0 | 0 |
| Storm Water Drainage | - | 7.79 | 7.79 | 7.79 |
| Water Supply System | - | 9.74 | 9.74 | 9.74 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 16.23 | 16.23 | 16.23 | 16.23 |
| Other | 1.95 | 1.95 | 1.95 | 1.95 |
| Parks and Playgrounds | 3.26 | 3.26 | 3.26 | 3.26 |
| Roads & Pavements | 11.69 | 11.69 | 11.69 | 11.69 |
| Sewerage treatment & garbage disposal | 14.29 | 14.29 | 14.29 | 14.29 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 7.79 | 7.79 | 7.79 | 7.79 |
| Water Supply System | 9.74 | 9.74 | 9.74 | 9.74 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 16.23 | 16.23 | 16.23 | 16.23 |
| Other | 1.95 | 1.95 | 1.95 | 1.95 |
| Parks and Playgrounds | 3.26 | 3.26 | 3.26 | 3.26 |
| Roads & Pavements | 11.69 | 11.69 | 11.69 | 11.69 |
| Sewerage treatment & garbage disposal | 14.29 | 14.29 | 14.29 | 14.29 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 7.79 | 7.79 | 7.79 | 7.79 |
| Water Supply System | 9.74 | 9.74 | 9.71 | 9.74 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 16.23 | 16.23 | 16.23 | 16.23 |
| Other | 1.95 | 1.95 | 1.95 | 1.95 |
| Parks and Playgrounds | 3.26 | 3.26 | 3.26 | 3.26 |
| Roads & Pavements | 11.69 | 11.69 | 11.69 | 11.69 |
| Sewerage treatment & garbage disposal | 14.29 | 14.29 | 14.29 | 14.29 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 7.79 | 7.79 | 7.79 | 7.79 |
| Water Supply System | 9.74 | 9.74 | 9.74 | 9.74 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 16.23 | 16.23 | 16.23 | 32.48 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 3.26 | 3.26 | 3.26 | 6.49 |
| Roads & Pavements | 11.69 | 11.69 | 11.69 | 23.38 |
| Sewerage treatment & garbage disposal | 14.29 | 14.29 | 14.29 | 28.57 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 7.79 | 7.79 | 7.79 | 15.59 |
| Water Supply System | 9.74 | 9.74 | 9.74 | 19.48 |
Dream Valley (Sector-7, Jhajjar) is located in Jhajjar.
Yes. Dream Valley (Sector-7, Jhajjar) is registered under RERA-PKL-2091-2026 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Dream Valley (Sector-7, Jhajjar) is 27 January 2031.