Launch Date
Completion Date
RERA ID
28.4930
78.4245
DEMARCATION OF PLOTS IS DONE THROUGH BRICK WORKS OF 4.5 INCH IN ZIG-ZAG PATTERN.
EXISTING BOUNDARY WALLS OF 6 FEET HEIGHT AND 9 INCH THICK THROUGH BRICK WORK AND FOUNDATION BRICK WORK OF 4 FEET UNDER THE GROUND STARTING WALL FOUNDATION FRO 22INCH THICKNESS GOING UP TO 18 INCH AND THEN 14 INCH AND FINALLY 9 INCH AND COLUMN IN BRICK BOUNDARY WALL AND PLASTER WORK IN INNER SIDE AND PLASTER WORK IN FRONT BOTH SIDE.
9METER INTERNAL ROAD WILL BE MADE BY RAMMED EARTH AND THEN 150MM WBM 40-63 STONE/BAJRA AND THEN 150 MM THICK PCC AND THEN 125 MM THICK CONCRETE/RCC.
WILL BE MADE BY RAMMED EARTH AND THEN 100 MM WBM 40-63 STONE/BAJRA AND THEN SAND WORK AFTER THAT PAVERS WILL BE INSTALLED.
WATER SUPPLY SHALL BE DONE TILL PARK AREA DRINKING WATER FACILITY TO BE DONE BY RESIDENTS.
SEWER SYSTEM WILL BE MADE UNDER GROUND WHICH CONSIST BY RAMMED EARTH AND THEN 100MM THICK PCC AND THEN HDPE PIPES DOUBLE WALL AND THEN PCC.
DRAIN WILL CONSIST OF HDPE PIPE DOUBLE WALL AND MAIN HOLES IN REGULAR INTERVAL.
WATER BDIES/LANDSCAPE AND KIDS PLAY AREA ALONG WITHGREEN AREA WOULD BE DEVELOPED.
THE TREES WILL BE PLANTED AT ALL SUITABLE LOCATIONS OF THE PROJECT AND ALONG THE BOUNDARY WALL.
ELECTRICAL LAYOUT AND CAPACITY WILL BE INSTALLED TO SUFFICE THE RESIDENTIAL USE . ALL ELECTRICAL CABLING WILL BE UNDERGROUND AND STREET LIGHTS WILL BE AS PER WORKING DRAWINGS. ELECTRICITY SUPPLY SHALL BE DONE THROUGH IRON POLES AS PER THE ELECTICITY PLANS.
NA
ALL WASTE OF SEWER LINE TO BE COLLECTED AT STP, AFTER TREATMENT WATER TO BEUSED FOR WATERINGOF THE GREEN AREA, RWH LINE IS PLANNED TO COLLECT WATER FROM DRAINAND TO BE DIRECTED TO MULTIPLE RECHARGE PITS, IRIIGATIONOF PLANT BY FLUSH-WATER SYSTEM, AS PER LAYOUT. STANDARD STP SYSTEM WITH 40KLD
ALL WASTE OF SEWER LINE TO BE COLLECTED AT STP, GARBAGE COLLECTION TO BE DONE THROUGHAUTHORISED AGENCY AND TO BE DISPOSED AT GARBAGE DISPOSAL AREA AS PER SANCTION PLAN. OR STP/COMPOSTING PIT
RAIN WATER HARVESTING LINE TO BE LAID , IRRIGATION OF PLANT BY FLUSH- WATER SYSTEM, AS PER SANCTIONED LAYOUT RWH LINE IS PLANNED TO COLLECT WATER FROM DRAIN AND TO BEDIRECTED TO MULTIPLE RECHARGE PITS, IRRIGATION OF PLANT BY FLUSH WATER SYSTEM AS PER LAYOUT. .
NA
NA
NA
NA
NA
Showing 1 blocks with 2 units
Total Carpet Area
0.00 m²
0.00 ft²
Total Units
0
1 different types
Blocks & Floors
1
1 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
23839.00 m²
256600.61 ft²