Land Area
Project Size
Density
Unit Configurations
Size
Total Floors
RERA Received
RERA Completion
Launch Price
Current Price
RERA ID
BSP only. GST, PLC, Parking, IFMS could be add ons.





Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | 0 | 0 |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | - | - | 0 | 0 |
| Other | - | - | 0 | 0 |
| Parks and Playgrounds | - | - | 0 | 0 |
| Rain Water Harvesting | - | - | - | - |
| Renewable Energy System | - | - | - | - |
| Roads & Pavements | - | - | 0 | 11.6 |
| STP | - | - | 13.04 | 13.04 |
| Security and fire fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | - | - | 0 | 0 |
| Shopping area | - | - | 0 | 0 |
| Storm Water Drainage | - | - | 0 | 0 |
| Street Lighting | - | - | - | - |
| Underground water tank | - | - | 2.03 | 2.03 |
| Water Supply System | - | - | 0 | 13.56 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Sub Station | - | - | - | - |
| Electricity Supply System | 17.08 | 17.08 | 17.08 | 17.08 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 2.84 | 2.84 | 2.84 | 2.84 |
| Rain Water Harvesting | 0 | 21.34 | 21.34 | 21.34 |
| Renewable Energy System | 0 | 0.79 | 0.79 | 0.79 |
| Roads & Pavements | 11.6 | 11.6 | 11.6 | 11.6 |
| STP | 13.04 | 13.04 | 13.04 | 13.04 |
| Security and fire fighting | 77.9 | 77.9 | 77.9 | 77.9 |
| Sewerage treatment & garbage disposal | 10.68 | 10.68 | 10.68 | 10.68 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3.44 | 3.44 | 3.44 | 3.44 |
| Street Lighting | 1.02 | 1.02 | 1.02 | 1.02 |
| Underground water tank | 2.03 | 2.03 | 2.03 | 2.03 |
| Water Supply System | 13.56 | 13.56 | 13.56 | 13.56 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Sub Station | 64.7 | 64.7 | 64.7 | 64.7 |
| Electricity Supply System | 17.08 | 17.08 | 34.17 | 34.17 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 2.84 | 2.84 | 5.67 | 5.67 |
| Rain Water Harvesting | 21.34 | 21.34 | 42.68 | 42.68 |
| Renewable Energy System | 0.79 | 0.79 | 1.59 | 1.59 |
| Roads & Pavements | 11.6 | 23.2 | 23.2 | 23.2 |
| STP | 13.04 | 13.04 | 13.04 | 13.04 |
| Security and fire fighting | 77.9 | 77.9 | 155.8 | 155.8 |
| Sewerage treatment & garbage disposal | 10.68 | 10.68 | 21.35 | 21.35 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 3.44 | 6.88 | 6.88 | 6.88 |
| Street Lighting | 1.02 | 1.02 | 2.04 | 2.04 |
| Underground water tank | 2.03 | 2.03 | 2.03 | 2.03 |
| Water Supply System | 13.56 | 27.13 | 27.13 | 27.13 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electrical Sub Station | 64.7 | 64.7 | 64.7 | 64.7 |
| Electricity Supply System | 34.17 | 34.17 | 34.17 | 34.17 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 5.67 | 5.67 | 5.67 | 5.67 |
| Rain Water Harvesting | 42.68 | 42.68 | 42.68 | 42.68 |
| Renewable Energy System | 1.59 | 1.59 | 1.59 | 1.59 |
| Roads & Pavements | 23.2 | 23.2 | 11.6 | 11.6 |
| STP | 13.04 | 26.08 | 26.08 | 26.08 |
| Security and fire fighting | 155.8 | 155.8 | 155.8 | 155.8 |
| Sewerage treatment & garbage disposal | 21.35 | 21.35 | 21.35 | 21.35 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 6.88 | 6.88 | 6.88 | 3.44 |
| Street Lighting | 2.04 | 2.04 | 2.04 | 2.04 |
| Underground water tank | 2.03 | 4.07 | 4.07 | 4.07 |
| Water Supply System | 27.13 | 27.13 | 13.56 | 13.56 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | - | - |
| Electrical Sub Station | 64.7 | 64.7 | - | - |
| Electricity Supply System | 17.08 | 17.08 | - | - |
| Other | 0 | 0 | - | - |
| Parks and Playgrounds | 2.84 | 2.8 | - | - |
| Rain Water Harvesting | 42.68 | 21.38 | - | - |
| Renewable Energy System | 1.59 | 0.82 | - | - |
| Roads & Pavements | 11.6 | 11.64 | - | - |
| STP | 26.08 | 13.03 | - | - |
| Security and fire fighting | 77.9 | 77.9 | - | - |
| Sewerage treatment & garbage disposal | 10.68 | 10.68 | - | - |
| Shopping area | 0 | 0 | - | - |
| Storm Water Drainage | 3.44 | 3.46 | - | - |
| Street Lighting | 1.02 | 1.02 | - | - |
| Underground water tank | 4.07 | 2.09 | - | - |
| Water Supply System | 13.56 | 13.58 | - | - |
Conscient Elevate Vista is located in Sector 63A, Gurgaon. The project is spread across 7.82 acres.
Yes. Conscient Elevate Vista is registered under RERA-GRG-2308-2026 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Conscient Elevate Vista is 30 September 2034.
Conscient Elevate Vista is developed by Conscient.
Conscient Elevate Vista offers 3 BHK and 4 BHK configurations.
Developed by
8 Projects
EXECUTIVE SUMMARY OF CONSCIENT Conscient Infrastructure Private Limited is a privately held real estate developer incorporated in Delhi in 1990, with roots tracing back to a family-driven group established in the mid-197…
Know More about Conscient