| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| BRICK WORK | - | - | - | - |
| CASTING OF FIRST FLOOR | - | - | - | - |
| CASTING OF GROUND FLOOR | - | - | - | - |
| CASTING OF SECOND FLOOR | - | - | - | - |
| CASTING OF THIRD FLOOR | - | - | - | - |
| Clubhouse/community centres | - | - | 0 | 0 |
| EXCAVATION WORK | - | - | - | 50 |
| EXTERNAL FINISHING WORK | - | - | - | - |
| Electricity Supply System | - | - | 0 | 0 |
| FINISHING WORK OF COMMON AREA AND STAIRCASE AND LIFT | - | - | - | - |
| FINISHING WORK OF COMMON AREA AND STAIRCASE AND LIFTS | - | - | - | - |
| FINISHING WORK OF COMMON AREAS AND STAIRCASE AND LIFTS | - | - | - | - |
| FIRE FIGHTING SCHEME | - | - | - | - |
| FOUNDATION AND CASTING OF BASEMENT ONE AND TWO | - | - | - | 200 |
| OPEN AREA FINISHINGS | - | - | - | - |
| Other | - | - | 0 | 0 |
| PLASTER WORK | - | - | - | - |
| Parks and Playgrounds | - | - | 0 | 0 |
| RAIN WATER HARVESTING SYSTEM | - | - | - | - |
| RENEWABLE SOLAR ENERGY SYSTEM | - | - | - | - |
| Roads & Pavements | - | - | 0 | 0 |
| Sewerage treatment & garbage disposal | - | - | 0 | 0 |
| Shopping area | - | - | 0 | 0 |
| Storm Water Drainage | - | - | 0 | 0 |
| Water Supply System | - | - | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| BRICK WORK | - | 40 | 40 | 40 |
| CASTING OF FIRST FLOOR | - | - | 150 | - |
| CASTING OF GROUND FLOOR | - | 150 | - | - |
| CASTING OF SECOND FLOOR | - | - | - | 150 |
| CASTING OF THIRD FLOOR | - | - | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| EXCAVATION WORK | - | - | - | - |
| EXTERNAL FINISHING WORK | - | - | - | - |
| Electricity Supply System | 0 | 3 | 2 | 2 |
| FINISHING WORK OF COMMON AREA AND STAIRCASE AND LIFT | - | - | - | - |
| FINISHING WORK OF COMMON AREA AND STAIRCASE AND LIFTS | - | - | - | 30 |
| FINISHING WORK OF COMMON AREAS AND STAIRCASE AND LIFTS | - | - | - | - |
| FIRE FIGHTING SCHEME | - | - | - | - |
| FOUNDATION AND CASTING OF BASEMENT ONE AND TWO | 250 | - | - | - |
| OPEN AREA FINISHINGS | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| PLASTER WORK | - | - | 10 | 30 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| RAIN WATER HARVESTING SYSTEM | - | - | - | - |
| RENEWABLE SOLAR ENERGY SYSTEM | - | - | - | - |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Water Supply System | 0 | 2 | 8 | 8 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| BRICK WORK | 40 | 50 | 70 | - |
| CASTING OF FIRST FLOOR | - | - | - | - |
| CASTING OF GROUND FLOOR | - | - | - | - |
| CASTING OF SECOND FLOOR | - | - | - | - |
| CASTING OF THIRD FLOOR | 150 | - | - | - |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| EXCAVATION WORK | - | - | - | - |
| EXTERNAL FINISHING WORK | 30 | 80 | 90 | - |
| Electricity Supply System | 2 | 3 | 3 | 0 |
| FINISHING WORK OF COMMON AREA AND STAIRCASE AND LIFT | - | - | 100 | - |
| FINISHING WORK OF COMMON AREA AND STAIRCASE AND LIFTS | - | 60 | - | - |
| FINISHING WORK OF COMMON AREAS AND STAIRCASE AND LIFTS | 60 | - | - | - |
| FIRE FIGHTING SCHEME | - | 25 | 25 | - |
| FOUNDATION AND CASTING OF BASEMENT ONE AND TWO | - | - | - | - |
| OPEN AREA FINISHINGS | 40 | 80 | 85 | - |
| Other | 0 | 0 | 0 | 0 |
| PLASTER WORK | 30 | 42 | 30 | - |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| RAIN WATER HARVESTING SYSTEM | - | 7 | - | - |
| RENEWABLE SOLAR ENERGY SYSTEM | - | - | 8 | - |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Water Supply System | 8 | 7 | 7 | 0 |
Ceremony Enthia is located in Panipat.
Yes. Ceremony Enthia is registered under RERA-PKL-1311-2023 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Ceremony Enthia is 30 September 2025.
Ceremony Enthia is developed by CEREMONYHOMES PRIVATE LIMITED.