NEWActive

BPTP PARKLANDS

FARIDABAD, FARIDABAD
20-03-2024
Launch Date
NEW
Type
2029-03-31
Completion Date

Overview

Launch Date

20-03-2024

Completion Date

2029-03-31

RERA ID

RERA-PKL-1441-2024

Basic Details

Project NameBPTP PARKLANDS
Project IDRERA-PKL-1441-2024
Project TypeNEW
Applicant TypeCompany
Submission Date20-03-2024 08:32:20 PM
Builder NameCOUNTRYWIDE PROMOTERS PRIVATE LIMITED
CINU70101HR1996PTC082720
PANXXXX280H
Emailrera.panchkula@bptp.com
Websitehttp://bptp.com
Phone (Mobile)9717790021
Phone (Landline)01149572787
Registered AddressOT-14, 3RD FLOOR, NEXT DOOR PARKLANDS, SECTOR-76 FARIDABD FARIDABAD HR 121004 IN
Project AddressSECTOR 82 TO 89 FARIDABAD
DistrictFARIDABAD
TehsilFARIDABAD

Bank Details

Bank NameICICI BANK LTD.,SCF NO-62-63, GROUND FLOOR SECTOR 15 HUDA MARKET SECTOR 15 FARIDABAD-121007 HARYANA
Account Number777705300195
IFSC CodeICIC0001660
MICR Code110229132
Branch Code001660

Account Related Information

Annex copy of the balance sheet of last 3 yearsYes
In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.No
Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)Mr. Kabul Chawla Address: 7, Amrita Shergill Marg Delhi-110003 Mr. Sudhanshu Tripathi Address: 202, 3rd Floor,Jor Bagh, , Delhi -110003 Mr. Manik Malik D-2/2406, VasantKunj, South West Delhi, Delhi- 110070 Mr. Sachin GuptaH.No C-5/32. Yamuna Vihar, Delhi -110053 Mr. RakeshKumar Agrawal D-308 , Narwana Apartment , 89, IPExtension , Patparganj Delhi- 110092 Mr. Amit SinghalAddress: E3/28, Nand Nagri Mandoli Delhi-110093 Mr.Rajan Nayyar Address: H.no-152/12 Near Shiv Mandir Krishna Colony Gurugram Haryana- 122001 Mr. Sanjeev Loknath Agrawal Flat no 32 Sudarshan Apartments IPExtension Delhi -110092
Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)As Attached

Development Details

Land Area18.30625 (Acre)
Proposed FAR1
Permissible FAR1
Total Licensed Land571.30625 (Acre)

Land Usage

PLOTS TO BE SOLD7.01
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
CONSTRUCTION OF ROADS5.74625
PAVEMENTS0
PARKS AND PLAYGROUNDS0
GREEN BELTS1.04
VEHICLE PARKINGS0
ELECTRICITY SUB-STATION0
CLUB HOUSE0
SEWAGE AND SOLID WASTE TREATMENT FACILITY0
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
ANY OTHER0
EWS PLOTS0.75
PART OF COMMERCIAL POCKET0.65
PRIMARY SCHOOL1
TWO NURSERY SCHOOL0.40
POLICE POST1
PART OF HEALTH CENTRE0.71
Total18.30625

Cost Details

Land Cost3295 Lakhs
Other Cost2561.07 Lakhs
Estimated Project Cost6488.07 Lakhs
Estimated Infrastructure Cost632 Lakhs
Estimated Apartment Construction Cost0 Lakhs

Documents

COPY OF LICENSE ALONG WITH SCHEDULE OF LAND

Uploaded on: 20-03-2024

IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN

Uploaded on: 20-03-2024

IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN

Uploaded on: 20-03-2024

NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT

Uploaded on: 20-03-2024

DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.

Uploaded on: 20-03-2024

Statutory Approvals

LICENSE NO 54 OF 2024Date: 15-03-2024Status: ALREADY BEEN OBTAINED
LAYOUT APPROVALDate: 15-03-2024Status: ALREADY BEEN OBTAINED
ZONING APPROVALDate: 25-04-2024Status: ALREADY BEEN OBTAINED
Lay out PlanApproved: Yes
Demarcation PlanApproved: No
Zoning PlanApproved: Yes
Building PlanApproved: No
Site PlanApproved: No
Floor PlanApproved: No
Apartment PlansApproved: No
Elevation SectionApproved: No
Detail of Permissible FARApproved: No
Detail of covered area achieved FARApproved: No

Facilities

INTERNAL ROADS AND PAVEMENTSYET TO BE PREPARED
WATER SUPPLY SYSTEMYET TO BE PREPARED
STORM WATER DRAINAGEYET TO BE PREPARED
ELECTRICITY SUPPLY SYSTEMYET TO BE PREPARED
SEWAGE TREATMENT & GARBAGE DISPOSALYET TO BE PREPARED
STREET LIGHTINGYET TO BE PREPARED
SECURITY AND FIRE FIGHTINGYET TO BE PREPARED
PLAYGROUNDS AND PARKSYET TO BE PREPARED
CLUB HOUSE/COMMUNITY CENTREYET TO BE PREPARED
SHOPPING AREAYET TO BE PREPARED
RENEWABLE ENERGY SYSTEMYET TO BE PREPARED
SCHOOLYET TO BE PREPARED
HOSPITAL/DISPENSARYYET TO BE PREPARED
ANY OTHERYET TO BE PREPARED
RAIN WATER HARVESTINGYET TO BE PREPARED

NOC

ROADSProvider: HSVPApproval Status: Pending
WATER SUPPLYProvider: HSVPApproval Status: Pending
ELECTRICITYProvider: DHBVNApproval Status: Pending
SEWAGE DISPOSALProvider: HSVPApproval Status: Pending
STORM WATER DRAINAGEProvider: HSVPApproval Status: Pending

Project Team

Authorized Representative

RAHUL SHARMA
Name
RAHUL SHARMA
PAN
XXXX795N
Email
rera.panchkula@bptp.com
Mobile
9717790021
Landline
01149572787
Address
R 14 A Mohan Garden Uttam Nagar New Delhi 110059

Managing Director/CEO

RAJESH KUMAR
Name
RAJESH KUMAR
PAN
XXXX433E
Email
rera.panchkula@bptp.com
Mobile
9818141605
Landline
01149572787
Address
A 2205 Phase 5 Ishwar Colony Aya Nagar South Delhi 110047

Directors

RAKESH ROSHAN
Name
RAKESH ROSHAN
PAN
XXXX973K
Email
rera.panchkula@bptp.com
Mobile
8800093101
Landline
01149572787
Address
7 Barakhamba Road New Delhi- 110001

Contact Details

Project ContactEmail: rera.panchkula@bptp.comMobile: 8800414400Landline: 8800414400
Project Contact PersonName: VINOD KUMAREmail: rera.panchkula@bptp.comMobile: 8800414400Landline: 8800414400

Land Details

Land Area18.30625 (Acre)
Proposed FAR1
Permissible FAR1
Total Licensed Land571.30625 (Acre)

Land Usage

Land Cost3295 Lakhs
Other Cost2561.07 Lakhs
Estimated Project Cost6488.07 Lakhs
Estimated Infrastructure Cost632 Lakhs
Estimated Apartment Construction Cost0 Lakhs

Total Infrastructure Expenditure

ParticularsExpenditure (in Lakhs)
Other0
Shopping area0
Street Lighting0
Roads & Pavements0
Water Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Rain water harvesting0
Electricity Supply System0
Clubhouse/community centres0
Sewerage treatment & garbage disposal0

Quarterly Infrastructure Expenditure

2024 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres-000
Electricity Supply System-777
Other-000
Parks and Playgrounds-666
Rain Water HArvesting----
Rain Water Harvestin----
Rain Water Harvesting-3.433.43.4
Rain Watre Harvesting----
Roads & Pavements-151515
Sewerage treatment & garbage disposal-222
Shopping area-000
Storm Water Drainage-333
Street Light----
Street Lightin---1
Street Lighting-11-
Water Supply System-222
2025 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electricity Supply System7777
Other0000
Parks and Playgrounds6666
Rain Water HArvesting----
Rain Water Harvestin-3.4--
Rain Water Harvesting3.4-3.43.4
Rain Watre Harvesting----
Roads & Pavements15151515
Sewerage treatment & garbage disposal2222
Shopping area0000
Storm Water Drainage3333
Street Light----
Street Lightin----
Street Lighting1111
Water Supply System2222
2026 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electricity Supply System7777
Other0000
Parks and Playgrounds6666
Rain Water HArvesting----
Rain Water Harvestin----
Rain Water Harvesting3.43.43.4-
Rain Watre Harvesting---3.4
Roads & Pavements15151515
Sewerage treatment & garbage disposal2222
Shopping area0000
Storm Water Drainage3333
Street Light1---
Street Lightin----
Street Lighting-111
Water Supply System2222
2027 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0000
Electricity Supply System7777
Other0000
Parks and Playgrounds6666
Rain Water HArvesting--3.4-
Rain Water Harvestin----
Rain Water Harvesting3.43.4-3.4
Rain Watre Harvesting----
Roads & Pavements15151515
Sewerage treatment & garbage disposal2222
Shopping area0000
Storm Water Drainage3333
Street Light----
Street Lightin----
Street Lighting1111
Water Supply System2222
2028 - Quarterly Expenditure (In Lakhs)
ParticularsJan-MarApr-JuneJuly-SepOct-Dec
Clubhouse/community centres0---
Electricity Supply System7---
Other0---
Parks and Playgrounds6---
Rain Water HArvesting----
Rain Water Harvestin----
Rain Water Harvesting3.4---
Rain Watre Harvesting----
Roads & Pavements15---
Sewerage treatment & garbage disposal2---
Shopping area0---
Storm Water Drainage3---
Street Light----
Street Lightin----
Street Lighting1---
Water Supply System2---

Other Details

Construction Specifications

FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
WALL FINISHING DETAILSNA
KITCHEN DETAILSNA
BATHROOM FITTINGSNA
WOOD WORK ETCNA
DOORS AND WINDOS FRAMESNA
GLASS WORKNA
ELECTRIC FITTINGSNA
CONDUCTING AND WIRING DETAILSNA
CUPBOARD DETAILSNA
WATER STORAGENA
LIFT DETAILSNA
EXTERNAL GLAZINGSNA
WINDOWS/GLAZINGSNA
DOORSNA
MAIN DOORSNA
INTERNAL DOORSNA
AIR CONDITIONINGNA
ELECTRICAL FITTINGSNA
CNG PIPE LINENA
PROVISION OF WIFI AND BROADBAND FACILITYNA
EXTERNAL FINISHING/COLOUR SCHEMENA
INTERNAL FINISHINGNA

Unit-wise Specifications

TOILET
FLOORNA
WALLSNA
CEILINGNA
COUNTERSNA
SANITARY WARE/CP FITTINGSNA
FIXTURESNA
KITCHEN
FLOORNA
WALLSNA
CEILINGNA
COUNTERSNA
FIXTURESNA
KITCHEN APPLIANCESNA
SIT-OUTS
FLOORNA
WALLS & CEILINGNA
RAILINGSNA
FIXTURESNA
BED ROOMS
FLOORNA
WALLSNA
CEILINGNA
WARDROBESNA
MASTER TOILET
FLOORNA
WALLSNA
CEILINGNA
COUNTERSNA
SANITARY WARE/CP FITTINGSNA
FITTING/FIXTURESNA
MASTER BEDROOM/DRESSROOM
FLOORNA
WALLSNA
CEILINGNA
MODULAR WARDROBESNA
LIVING/DINING/FOYER/FAMILY LOUNGE
FLOORNA
WALLSNA
CEILINGNA
UTILITY ROOMS/UTILITY BALCONY/TOILET
FLOORNA
WALLS & CEILINGNA
TOILETNA
BALCONYNA

Fee Details

Payment 1
amount:740828
cheque no:54479
draft date:20-03-2024
payable to:HRERA Panchkula
payee bank:INDUSIND BANK