Have queries on this Project?
Uploaded on: 08-03-2025
Uploaded on: 08-03-2025
Uploaded on: 08-03-2025
Uploaded on: 08-03-2025





| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Admin Expenses | 0.5 | 0.5 | 0.5 | 0.5 |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 8.5 |
| Lift | - | - | - | - |
| Marketing Expenses | 0.75 | 0.75 | 0.75 | 0.75 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Security and Fire Fighting | - | - | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 3.5 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 3.5 | 0 |
| Street Lighting | - | - | - | - |
| Super Structure | 25 | 25 | 0 | 0 |
| UGT | 0 | 0 | 18 | 7 |
| Water Supply System | 0 | 0 | 0 | 9.5 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Admin Expenses | 0.5 | 0.5 | 0.4 | - |
| Clubhouse/community centres | 0 | 0 | 0 | - |
| Electricity Supply System | 8.93 | 0 | 0 | - |
| Lift | 0 | - | 20 | - |
| Marketing Expenses | 0.75 | 0.75 | 0.6 | - |
| Other | 0 | 0 | 0 | - |
| Parks and Playgrounds | 0 | 0 | 0 | - |
| Roads & Pavements | 6.07 | 9.5 | 0 | - |
| Security and Fire Fighting | 0 | 8.5 | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | - |
| Shopping area | 0 | 0 | 0 | - |
| Storm Water Drainage | 0 | 0 | 0 | - |
| Street Lighting | 0 | 2 | - | - |
| Super Structure | - | - | - | - |
| UGT | 0 | 5 | - | - |
| Water Supply System | 10 | 0 | 0 | - |