Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | - | - | 31.86 | 31.86 |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| DWC Pipes for Electricity Distribution | - | - | - | 10.91 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Fire Fighting | - | - | - | - |
| Guard Room | - | - | - | - |
| Gurad Room | - | - | - | - |
| Meter and VCB Room | - | - | - | - |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 14.35 | 21.52 |
| Shopping area | 0 | 0 | 0 | 0 |
| Signages | - | - | - | - |
| Solar Power System | - | - | - | - |
| Storm Water Drainage | 0 | 0 | 13.41 | 17.88 |
| Street Lighting | - | - | - | - |
| Water Supply System | 0 | 0 | 0 | 41.6 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Boundary Wall | 0 | 0 | 0 | 0 |
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| DWC Pipes for Electricity Distribution | 10.91 | 10.91 | 0 | 0 |
| Electricity Supply System | 10.91 | 21.82 | 32.73 | 32.73 |
| Fire Fighting | - | - | 2.65 | - |
| Guard Room | 4 | - | 0 | 0 |
| Gurad Room | - | 0 | - | - |
| Meter and VCB Room | - | - | 7.16 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 4.76 | 4.77 | 4.77 | 4.76 |
| Roads & Pavements | 18.63 | 21.74 | 46.59 | 37.26 |
| Sewerage treatment & garbage disposal | 40.88 | 40.87 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Signages | - | - | - | 3 |
| Solar Power System | - | - | - | 32.74 |
| Storm Water Drainage | 13.42 | 0 | 0 | 0 |
| Street Lighting | - | 8.23 | 8.23 | 4.12 |
| Water Supply System | 41.6 | 33.71 | 30 | 0 |