Uploaded on: 11-06-2022
Uploaded on: 29-06-2022




| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | 0 | 0 |
| Electricity Supply System | - | - | 0 | 0 |
| Other | - | - | 0 | 50 |
| Parks and Playgrounds | - | - | 0 | 0 |
| Roads & Pavements | - | - | 50 | 50 |
| Sewerage treatment & garbage disposal | - | - | 50 | 50 |
| Shopping area | - | - | 0 | 0 |
| Storm Water Drainage | - | - | 15 | 15 |
| Street Light | - | - | - | - |
| Water Supply System | - | - | 40 | 20 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 100 | 100 | 100 | 100 |
| Other | 50 | 50 | 50 | 50 |
| Parks and Playgrounds | 30 | 30 | 30 | 30 |
| Roads & Pavements | 50 | 50 | 50 | 50 |
| Sewerage treatment & garbage disposal | 50 | 50 | 50 | 38.6 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 15 | 15 | 15 | 15 |
| Street Light | - | 10 | 10 | 10 |
| Water Supply System | 20 | 20 | 20 | 20 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | - | - |
| Electricity Supply System | 100 | 89.4 | - | - |
| Other | 0 | 0 | - | - |
| Parks and Playgrounds | 20 | 20.5 | - | - |
| Roads & Pavements | 50 | 8.5 | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | - | - |
| Shopping area | 0 | 0 | - | - |
| Storm Water Drainage | 20 | 18.2 | - | - |
| Street Light | 10 | 9.4 | - | - |
| Water Supply System | 20 | 21.82 | - | - |
Asha Bahadurgarh Phase-4 is located in Jhajjar.
Yes. Asha Bahadurgarh Phase-4 is registered under RERA-PKL-1048-2022 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Asha Bahadurgarh Phase-4 is 31 January 2027.
Asha Bahadurgarh Phase-4 is developed by GNEX REALTECH PVT. LTD..
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.