Rectangular Plot having 18479.65 sqm area, Accessible from 24 m wide road. Plot is 88.71m wide at the Front side, from the right = 190.37m, from the left =206.99 & the rear side is 88.98m wide.
Using 230 mm thick brick wall having ms grills on the top.
There are 6 m and 4.5 m wide internal road are provided. In which 6 m is for fire tender movement.
"750 mm wide footpath is provided. street lights, plantation and other services are also provided in footpath."
We have provided overhead tanks.
Centralized Sewerage system shall be Provided. All Sewerage water shall be go to the STP for tretement after treatement ,water shall be recycle and it will use in gardening and flushing system and oveflow from the STP shall be connect with the Municiple sewarage system.
Storm water drain shall be Provided. Storm water from Roof,Roads and other lanscape area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit to recharge the Ground water and overflow shall be connect with Municple drain line.
Green area/parks are located at the center of plot in two parts and third one is along the boundary wall.
Indegenious trees are proposed for planting.
We have design the system as per local electricity Board.
N/A
Centralized Sewerage system shall be Provided. All Sewerage water shall be go to the STP for tretement after treatement ,water shall be recycle and it will use in gardening and flushing system and oveflow from the STP shall be connect with the Municiple sewarage system.
For solid waste proper garbage collection area provided at site.
We will use low flow fixtures and rain water harvesting system to reduce the water consumption and improve the ground water level.
We will use energy efficient lights fitting in all area. In STP and Pump room all the equipment shall have energy efficient motor.
N/A
"Sewerage ,Storm water and water supply system shall be Provided. Transfer pumps to fill the domestic overhead tank. Water for domestic use & Flushing go down through gravity from domestic as well as flushing tanks. All Sewgage shall be go to the STP for recycling the water. Storm water for Roof,Roads and other area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municple drain."
3 no of exits are provided in each block, and staircase is open from the front.
N/A
Showing 19 blocks with 75 units
Total Carpet Area
21366.64 m²
229988.38 ft²
Total Units
944
2 different types
Blocks & Floors
19
4 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
17610.20 m²
189554.43 ft²