Have queries on this Project?
Uploaded on: 06-03-2024
Uploaded on: 06-03-2024

Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 26.34 | 13.67 | 13.67 | 13.67 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0.89 | 1.52 | 1.52 | 1.52 |
| Sewerage treatment & garbage disposal | 4.32 | 3.45 | 3.45 | 3.45 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 1.98 | 1.1 | 1.1 | 1.1 |
| Water Supply System | 4.58 | 1.4 | 1.4 | 1.4 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 13 | 15 | 10 | 12 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 2 | 0.5 | 0.5 | 4 |
| Sewerage treatment & garbage disposal | 3 | 4 | 5 | 3 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 1 | 2 | 1 | 1 |
| Water Supply System | 2 | 1.5 | 1 | 0.5 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 12 | 15 | 13.5 | 12.1 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 1.5 | 1 | 1.5 | 2 |
| Sewerage treatment & garbage disposal | 3 | 3.5 | 4 | 2.75 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 1 | 0.9 | 1.2 | 0.85 |
| Water Supply System | 1 | 1.3 | 0.9 | 1.7 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 12 | 15 | 13.5 | 12.1 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 1.5 | 1 | 1.5 | 2 |
| Sewerage treatment & garbage disposal | 3 | 3.5 | 4 | 2.75 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 1 | 1.2 | 1.2 | 0.85 |
| Water Supply System | 1 | 1.3 | 0.9 | 1.7 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 12 | 15 | 13.5 | 12.1 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 1.5 | 1 | 1.5 | 2 |
| Sewerage treatment & garbage disposal | 3 | 3.5 | 4 | 2.75 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 1 | 0.9 | 1.2 | 0.85 |
| Water Supply System | 1 | 1.3 | 0.9 | 1.7 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | - | - | - |
| Electricity Supply System | 12 | - | - | - |
| Other | 0 | - | - | - |
| Parks and Playgrounds | 0 | - | - | - |
| Roads & Pavements | 1.5 | - | - | - |
| Sewerage treatment & garbage disposal | 3 | - | - | - |
| Shopping area | 0 | - | - | - |
| Storm Water Drainage | 1 | - | - | - |
| Water Supply System | 1 | - | - | - |
Amolik Vibrante 79 is located in Faridabad.
Yes. Amolik Vibrante 79 is registered under RERA-PKL-1438-2024 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Amolik Vibrante 79 is 8 February 2029.
Amolik Vibrante 79 is developed by LOGERS REAL ESTATE BUILDERS LLP.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.