Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | 2.08 | 2.08 | 2.08 |
| Electricity Supply System | - | 17.11 | 16.61 | 20.06 |
| Other | - | 31.75 | 20.5 | 32.84 |
| Parks and Playgrounds | - | 0 | 0 | 0 |
| Roads & Pavements | - | 15.11 | 15.23 | 14.11 |
| Sewerage treatment & garbage disposal | - | 5.95 | 10.6 | 14.85 |
| Shopping area | - | 0 | 10.27 | 6.55 |
| Storm Water Drainage | - | 1.6 | 2.08 | 1.89 |
| Water Supply System | - | 17.5 | 17.5 | 17.5 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 2.08 | 2.08 | 2.08 | 2.08 |
| Electricity Supply System | 13.61 | 15.94 | 17.11 | 19.61 |
| Other | 34.5 | 28.99 | 30 | 33.69 |
| Parks and Playgrounds | 2.78 | 2.78 | 2.78 | 2.78 |
| Roads & Pavements | 16.22 | 15.17 | 18 | 12.34 |
| Sewerage treatment & garbage disposal | 14.85 | 13.9 | 14.85 | 14.9 |
| Shopping area | 8.55 | 9.77 | 4.5 | 5.5 |
| Storm Water Drainage | 2.14 | 2.04 | 1.89 | 2.08 |
| Water Supply System | 17.5 | 17.5 | 17.5 | 17.5 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 2.08 | 2.08 | 2.08 | 2.08 |
| Electricity Supply System | 13.61 | 17.61 | 16.11 | 15.95 |
| Other | 31.39 | 31.75 | 31.75 | 31.78 |
| Parks and Playgrounds | 2.78 | 2.78 | 2.78 | 2.78 |
| Roads & Pavements | 16.11 | 14.22 | 15.17 | 16.61 |
| Sewerage treatment & garbage disposal | 14.9 | 17.4 | 14.85 | 15.9 |
| Shopping area | 6.82 | 6.82 | 6.19 | 7.05 |
| Storm Water Drainage | 2.89 | 2.08 | 2.08 | 2.14 |
| Water Supply System | 17.5 | 17.5 | 17.5 | 17.5 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 2.08 | - | - | - |
| Electricity Supply System | 16.67 | - | - | - |
| Other | 31.64 | - | - | - |
| Parks and Playgrounds | 2.78 | - | - | - |
| Roads & Pavements | 13.73 | - | - | - |
| Sewerage treatment & garbage disposal | 12.09 | - | - | - |
| Shopping area | 3 | - | - | - |
| Storm Water Drainage | 2.08 | - | - | - |
| Water Supply System | 17.5 | - | - | - |
Amolik Blossom Woods is located in Faridabad.
Yes. Amolik Blossom Woods is registered under RERA-PKL-1289-2023 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Amolik Blossom Woods is 17 July 2028.
Amolik Blossom Woods is developed by G AND G BUILDTECH PRIVATE LIMITED.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.