| Particulars | Expenditure (in Lakhs) |
|---|---|
| Other | 0 |
| Shopping area | 0 |
| Roads & Pavements | 0 |
| Water Supply System | 0 |
| Storm Water Drainage | 0 |
| Parks and Playgrounds | 0 |
| Electricity Supply System | 0 |
| Clubhouse/community centres | 0 |
| Sewerage treatment & garbage disposal | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | - | - | 0 |
| Electricity Supply System | - | - | - | 0 |
| Horticulture | - | - | - | - |
| Hotriculture | - | - | - | 0.66 |
| Maintenance Charges | - | - | - | 6.51 |
| Other | - | - | - | 0 |
| Parks and Playgrounds | - | - | - | 0 |
| Roads & Pavements | - | - | - | 5.43 |
| Sewerage treatment & garbage disposal | - | - | - | 0.95 |
| Shopping area | - | - | - | 0 |
| Storm Water Drainage | - | - | - | 2.02 |
| Street Lighting | - | - | - | - |
| Street lighting | - | - | - | 4.28 |
| Water Supply System | - | - | - | 5.22 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Horticulture | - | - | - | - |
| Hotriculture | 0.66 | 0.66 | 0.66 | 0.55 |
| Maintenance Charges | 6.51 | 6.51 | 6.51 | 5.42 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 5.43 | 5.43 | 5.43 | 4.53 |
| Sewerage treatment & garbage disposal | 0.95 | 0.95 | 0.95 | 0.79 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 2.02 | 2.02 | 2.02 | 1.68 |
| Street Lighting | 4.28 | 4.28 | 4.28 | 3.56 |
| Street lighting | - | - | - | - |
| Water Supply System | 5.22 | 5.22 | 5.22 | 4.35 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Horticulture | - | - | - | - |
| Hotriculture | 0.55 | 0.55 | 0.55 | 0.44 |
| Maintenance Charges | 5.42 | 5.42 | 5.42 | 4.34 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 4.53 | 4.53 | 4.53 | 3.62 |
| Sewerage treatment & garbage disposal | 0.79 | 0.79 | 0.79 | 0.63 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 1.68 | 1.68 | 1.68 | 1.35 |
| Street Lighting | 3.56 | 3.56 | 3.56 | 2.85 |
| Street lighting | - | - | - | - |
| Water Supply System | 4.35 | 4.35 | 4.35 | 3.48 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Horticulture | 0.44 | 0.44 | 0.44 | 0.89 |
| Hotriculture | - | - | - | - |
| Maintenance Charges | 4.34 | 4.34 | 4.34 | 8.68 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 3.62 | 3.62 | 3.62 | 7.24 |
| Sewerage treatment & garbage disposal | 0.63 | 0.63 | 0.63 | 1.26 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 1.35 | 1.35 | 1.35 | 2.69 |
| Street Lighting | 2.85 | 2.85 | 2.85 | 5.7 |
| Street lighting | - | - | - | - |
| Water Supply System | 3.48 | 3.48 | 3.48 | 6.96 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Horticulture | 0.89 | 0.89 | 0.89 | 0.89 |
| Hotriculture | - | - | - | - |
| Maintenance Charges | 8.68 | 8.68 | 8.68 | 8.68 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Roads & Pavements | 7.24 | 7.24 | 7.24 | 7.24 |
| Sewerage treatment & garbage disposal | 1.26 | 1.26 | 1.26 | 1.26 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 2.69 | 2.69 | 2.69 | 2.69 |
| Street Lighting | 5.7 | 5.7 | 5.7 | 5.7 |
| Street lighting | - | - | - | - |
| Water Supply System | 6.96 | 6.69 | 6.96 | 6.96 |
Alpha Plaza is located in Karnal.
Yes. Alpha Plaza is registered under RERA-PKL-1022-2022 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for Alpha Plaza is 30 November 2026.