Have queries on this Project?
Uploaded on: 20-04-2021
Uploaded on: 27-07-2021
Uploaded on: 27-07-2021
Uploaded on: 02-09-2021







| Particulars | Expenditure (in Lakhs) |
|---|---|
| STP | 3.19 |
| Other | 0 |
| Shopping area | 0 |
| Street Lighting | 1.98 |
| Roads & Pavements | 4.98 |
| Water Supply System | 6.38 |
| Storm Water Drainage | 2 |
| Parks and Playgrounds | 0 |
| Rain Water Harvesting | 1.32 |
| Electrical Sub Station | 4.98 |
| Underground Water Tank | 0.74 |
| Renewable Energy System | 2.65 |
| Electricity Supply System | 38.48 |
| Security and Firefighting | 45.03 |
| Clubhouse/community centres | 0 |
| Construction of Circulation Road | 3.19 |
| Sewerage treatment & garbage disposal | 1.06 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | - | 0 | 0 | 0 |
| Construction of Circulation Road | - | 0 | 0 | 0 |
| Electrical Sub Station | - | 0 | 0 | 0 |
| Electrical Sub station | - | - | - | - |
| Electricity Supply System | - | 0 | 0 | 0 |
| Other | - | 0 | 0 | 0 |
| Parks and Playgrounds | - | 0 | 0 | 0 |
| Rain Water Harvesting | - | 0 | 0 | 0 |
| Renewable Energy System | - | 0 | 0 | 0 |
| Roads & Pavements | - | 0 | 0 | 0 |
| STP | - | 0 | 0 | 0 |
| Security and Firefighting | - | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | - | 0 | 0 | 0 |
| Shopping area | - | 0 | 0 | 0 |
| Storm Water Drainage | - | 0 | 0 | 0 |
| Street Lighting | - | 0 | 0 | 0 |
| Underground Water Tank | - | 0 | 0 | 0 |
| Water Supply System | - | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction of Circulation Road | 0 | 0 | 0 | 0 |
| Electrical Sub Station | 0 | 0 | 0 | 0 |
| Electrical Sub station | - | - | - | - |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | 0 | 0 | 0 | 0 |
| Renewable Energy System | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| STP | 0 | 0 | 0 | 0 |
| Security and Firefighting | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Street Lighting | 0 | 0 | 0 | 0 |
| Underground Water Tank | 0 | 0 | 0 | 0 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction of Circulation Road | 0 | 0 | 0 | 0 |
| Electrical Sub Station | 0 | 0 | 0 | - |
| Electrical Sub station | - | - | - | 0 |
| Electricity Supply System | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | 0 | 0 | 0 | 0 |
| Renewable Energy System | 0 | 0 | 0 | 0 |
| Roads & Pavements | 0 | 0 | 0 | 0 |
| STP | 0 | 0 | 0 | 0 |
| Security and Firefighting | 0 | 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 | 0 | 0 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 0 | 0 |
| Street Lighting | 0 | 0 | 0 | 0 |
| Underground Water Tank | 0 | 0 | 0 | 0 |
| Water Supply System | 0 | 0 | 0 | 0 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction of Circulation Road | 0 | 0 | 18.35 | 18.35 |
| Electrical Sub Station | 0 | 0 | - | - |
| Electrical Sub station | - | - | 28.61 | 28.61 |
| Electricity Supply System | 0 | 0 | 221.24 | 221.24 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | 0 | 0 | 7.59 | 7.59 |
| Renewable Energy System | 0 | 0 | 15.26 | 15.26 |
| Roads & Pavements | 0 | 0 | 28.6 | 28.6 |
| STP | 0 | 0 | 18.35 | 18.35 |
| Security and Firefighting | 0 | 0 | 258.87 | 258.87 |
| Sewerage treatment & garbage disposal | 0 | 0 | 6.12 | 6.12 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 11.5 | 11.5 |
| Street Lighting | 0 | 0 | 11.38 | 11.38 |
| Underground Water Tank | 0 | 0 | 4.28 | 4.28 |
| Water Supply System | 0 | 0 | 36.7 | 36.7 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Construction of Circulation Road | 18.35 | 18.35 | 36.7 | 36.7 |
| Electrical Sub Station | 28.61 | 28.61 | 57.22 | 57.22 |
| Electrical Sub station | - | - | - | - |
| Electricity Supply System | 221.24 | 221.24 | 442.49 | 442.49 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 | 0 | 0 |
| Rain Water Harvesting | 7.59 | 7.59 | 15.17 | 15.17 |
| Renewable Energy System | 15.26 | 15.26 | 30.52 | 30.52 |
| Roads & Pavements | 28.63 | 28.63 | 57.26 | 57.26 |
| STP | 18.35 | 18.35 | 36.7 | 36.7 |
| Security and Firefighting | 258.87 | 258.87 | 517.74 | 517.74 |
| Sewerage treatment & garbage disposal | 6.12 | 6.12 | 12.23 | 12.23 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 11.5 | 11.5 | 23 | 23 |
| Street Lighting | 11.38 | 11.38 | 22.76 | 22.76 |
| Underground Water Tank | 4.28 | 4.28 | 8.56 | 8.56 |
| Water Supply System | 36.7 | 36.7 | 73.4 | 73.4 |
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | - | - |
| Construction of Circulation Road | 0 | 0 | - | - |
| Electrical Sub Station | 0 | 0 | - | - |
| Electrical Sub station | - | - | - | - |
| Electricity Supply System | 0 | 0 | - | - |
| Other | 0 | 0 | - | - |
| Parks and Playgrounds | 0 | 0 | - | - |
| Rain Water Harvesting | 0 | 0 | - | - |
| Renewable Energy System | 0 | 0 | - | - |
| Roads & Pavements | 0 | 0 | - | - |
| STP | 0 | 0 | - | - |
| Security and Firefighting | 0 | 0 | - | - |
| Sewerage treatment & garbage disposal | 0 | 0 | - | - |
| Shopping area | 0 | 0 | - | - |
| Storm Water Drainage | 0 | 0 | - | - |
| Street Lighting | 0 | 0 | - | - |
| Underground Water Tank | 0 | 0 | - | - |
| Water Supply System | 0 | 0 | - | - |
AIPL Autograph is located in Sector 66, Gurgaon.
Yes. AIPL Autograph is registered under RERA-GRG-818-2021 with the Haryana RERA (HARERA), ensuring transparency and buyer protection.
As per the RERA filing, the expected possession date for AIPL Autograph is 8 April 2026.
AIPL Autograph is developed by AIPL.
Yes, home loan facilities are available from most major banks. You can compare interest rates and check your eligibility through our home loan services.
Developed by
9 Projects
EXECUTIVE SUMMARY Advance India Projects Limited (AIPL) is a closely-held public limited company incorporated in May 1997 and headquartered at The Masterpiece, Golf Course Road, Sector 54, Gurugram, Haryana. The group tr…