Launch Date
Completion Date
RERA ID
25.293586
82.935922
Demarcation was already done
More than 60 percent work done (brick Boundary wall).
Cement Concrete Internal cc Roads work will be done
nterlocking Pavers on PCC & compacted surface
To be provided by self system boring
Under Ground System and Main Sewer line has been designed as per norms
Underground system using RCC
NA
Tree Planting has been designed by by as per authority guidelines
Design has been done as per UP Electricity Board Guidelines
NA
Sewage will be treated for recycling (If required) otherwise, it will be connect with main line
Door to door collection & will be disposed up to garbage point
Recycling of treated water and rain water system to be provided
NA
System will be provided as per the fire department guidelines . NOC taken and soft copy uploaded in other plan data in document uploading section
NA
Provision of Exit Sign & Emergency Lights as per norms
NA
Showing 1 blocks with 36 units
Total Carpet Area
2645.55 m²
28476.44 ft²
Total Units
36
1 different types
Blocks & Floors
1
9 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
5338.66 m²
57464.80 ft²