Have queries on this Project?
Uploaded on: 28-03-2019
Uploaded on: 27-03-2019
Uploaded on: 28-03-2019







Infrastructure Total Expenditure
No total expenditure data is currently available for this project.
| Particulars | Jan-Mar | Apr-June | July-Sep | Oct-Dec |
|---|---|---|---|---|
| Clubhouse/community centres | 0 | 0 | 0 | 0 |
| Electricity Supply System | 0 | 10.59 | 60 | 48 |
| Other | 0 | 0 | 0 | 0 |
| Parks and Playgrounds | 14.44 | 5 | 5 | 10 |
| Roads & Pavements | 0 | 1.33 | 85 | 0 |
| Sewerage treatment & garbage disposal | 6.66 | 5 | 100 | 20 |
| Shopping area | 0 | 0 | 0 | 0 |
| Storm Water Drainage | 0 | 0 | 24.72 | 0 |
| Water Supply System | 0 | 51.35 | 50 | 0 |